Loading
Page views this IP this session = 1 of 10 unsubscribed pagesClochnahill Wind Farm
Click here for Generation Forecast for wind farms based on Met office data
Clochnahill Wind Farm (Wind , Active) Location in the UK : Scotland, Aberdeenshire Type of installation: Wind on/offshore: on Turbines :3 Capacity : 6 MW Approx Date of 1st power generation: Jan 2012
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
July 2008: Permission has been granted for a 4 turbine wind farm in Aberdeenshire south of Stonehaven.
Model: |
Siemens SWT 1.3
|
Start Speed: |
3
|
Capacity: |
1.3
|
Optimal Speed: |
14
|
Rotor Diameter: |
62
|
Stop Speed: |
25
|
Hub Height |
60 Avg for all turbines:60
|
Avg. Elevation: |
187
|
Web Page: |
|
Comment: |
|
Clochnahill Stonehaven AB39 2XY Scotland
Relationship |
Company (For:
Clochnahill
) |
Sorry I found no matches, Please try again.
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Clochnahill Wind Farm 5.2 MW
|
Energy Type: |
Wind Onshore |
County: |
Grampian Country: Scotland LPA: Aberdeenshire Council
|
Site ID and Reference: |
2839 / B0626
District:
|
Applicant: |
Private Developer
Application :
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
4 |
Turbine Capacity: |
1.3 |
Height of Turbines: |
|
Calculated capacity: |
5.2 |
Site Address: |
Clochnahill, Stonehaven AB39 2XY
|
|
|
County: |
Grampian Region: Scotland
|
OS Coordinates: |
382413 / 382413
|
Development Status: |
Operational
|
Application Submitted: |
7/27/2006
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
|
|
|
Generator Live |
1/20/2012
|
This Record Last Updated: |
2/26/2013
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Clochnahill Windfarm 6 MW
|
Energy Type: |
Wind Onshore |
County: |
Grampian Country: Scotland LPA: Aberdeenshire Council
|
Site ID and Reference: |
3265 / N00388W
District:
|
Applicant: |
Private Developer
Application :
ENQ/2005/0667
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
3 |
Turbine Capacity: |
2 |
Height of Turbines: |
|
Calculated capacity: |
6 |
Site Address: |
Clochnahill Farm
Temple of Fiddes
Mearns
Aberdeenshire
|
|
|
County: |
Grampian Region: Scotland
|
OS Coordinates: |
381637 / 381637
|
Development Status: |
Planning Permission Refused
|
Application Submitted: |
5/8/2006
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
3/20/2007
|
Construction Date: |
|
|
|
Generator Live |
|
This Record Last Updated: |
11/16/2007
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
3/20/2007 |
Capacity: 12 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 25 m/s (55.925 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 11/23/2024 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Case Study - Medium Wind n 2016, Green Cat Renewable Developments Limited (GCRD) purchased the Deuchries Wind Farm project after the previous owner decided the project was no longer viable Source: greencat, Date and Time of entry: Friday, November 22, 2024 00:00
Little Crow Solar Park Little Crow Solar Park is in Lincolnshire and is situated 2.5km northwest of the village of Broughton and directly to the east of the British steelworks at Scunthorpe. Source: inrg, Date and Time of entry: Friday, November 22, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Monday, September 9, 2024 00:00
How many more wind turbines will the UK build?. The government says it wants to generate enough wind energy to be able to power every home in the UK by 2030. Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
|
|
©2017
Simon Mallett |
|