Page views this IP this session = 1 of 10 unsubscribed pagesWern Ddu Wind Farm
Click here for Generation Forecast for wind farms based on Met office data
Wern Ddu Wind Farm (Wind , Active) Location in the UK : Wales, North Wales, Merseyside & Cheshire Type of installation: Wind on/offshore: on Turbines :4 Capacity : 8 MW Approx Date of 1st power generation: March 2010
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
(Craig Lelo)
Located between Gwyddelwern & Ruthin in North Wales Wern Ddu lies at the eastern the edge of Strategic Search Area A; one of seven areas identified by the Welsh Assembly Government as being suited to development of this kind.
The scheme would provide electricity for the needs of at least 4,500 homes in the locality and would make a 6% contribution to the Area A 2010 target.
Model: |
Enercon E70
|
Start Speed: |
4
|
Capacity: |
2.3
|
Optimal Speed: |
13.5
|
Rotor Diameter: |
71
|
Stop Speed: |
31
|
Hub Height |
55 Avg for all turbines:55
|
Avg. Elevation: |
279
|
Web Page: |
http://www.enercon.de/en-en/61.htm |
Comment: |
Gearless, variable speed, single blade adjustment. Start and Stop: Guesstimate
|
Wern Ddugwyddelwern Corwen LL21 9SB Wales
Relationship |
Company (For:
Wern Ddu
) |
Developer | Tegni | Owner | Triodos |
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Wern Ddu Wind Farm 9.2 MW
|
Energy Type: |
Wind Onshore |
County: |
Clwyd Country: Wales LPA: Denbighshire County Council
|
Site ID and Reference: |
3592 / 04056W4
District:
|
Applicant: |
Tegni
Application :
6/2004/278/PS
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
4 |
Turbine Capacity: |
2.2999999999999998 |
Height of Turbines: |
|
Calculated capacity: |
9.2 |
Site Address: |
NW Corwen, Gwyddelwern, Corwen, Denbighshire
|
|
|
County: |
Clwyd Region: Wales
|
OS Coordinates: |
305800 / 305800
|
Development Status: |
Operational
|
Application Submitted: |
4/23/2004
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
1/26/2005
|
Construction Date: |
11/1/2009
|
|
|
Generator Live |
3/1/2010
|
This Record Last Updated: |
4/26/2010
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
1/26/2005 |
Site Name: |
Wern Ddu
|
Generator Type: |
On-shore wind (RO code = RQ)
|
Scheme : |
RO
|
Generator ID: |
R00190RQWA
|
Capacity: |
9140
|
Status: |
Live
|
Accreditation Date: |
4/23/2004
|
|
|
Commission Date: |
3/3/2010
|
|
|
Applicant: |
Triodos Renewables Ltd
|
Applicant Address: |
Triodos Bank
Deanery Road
Bristol
BS1 5AS
England
|
Address: |
Wern Ddu
gwyddelwern
Corwen
LL21 9SB
Wales
|
Site Name: |
Wern Ddu
|
Generator Type: |
Wind
|
Scheme : |
REGO
|
Generator ID: |
G01350NWWA
|
Capacity: |
9140
|
Status: |
Live
|
Accreditation Date: |
4/23/2004
|
|
|
Commission Date: |
3/3/2010
|
|
|
Applicant: |
Triodos Renewables Ltd
|
Applicant Address: |
Triodos Bank
Deanery Road
Bristol
BS1 5AS
England
|
Address: |
Wern Ddu
gwyddelwern
Corwen
LL21 9SB
Wales
|
|
Assumptions: Capacity: 9140kW 9.14 MW, Thus over the month Capacity * 720 hours per month = 6580.8 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/03/2018 | | | 2055 | 22.48% | Issued | 01/02/2018 | | | 1885 | 20.62% | Issued | 01/01/2018 | | | 2893 | 31.65% | Issued | 01/12/2017 | | | 2146 | 23.48% | Issued | 01/11/2017 | | | 1829 | 20.01% | Issued | 01/10/2017 | | | 3078 | 33.68% | Issued | 01/09/2017 | | | 1456 | 15.93% | Issued | 01/08/2017 | | | 1272 | 13.92% | Issued | 01/07/2017 | | | 1277 | 13.97% | Issued | 01/06/2017 | | | 1708 | 18.69% | Issued | 01/05/2017 | | | 1216 | 13.30% | Issued | 01/04/2017 | | | 1187 | 12.99% | Issued | 01/03/2017 | | | 2010 | 21.99% | Redeemed | 01/02/2017 | | | 2365 | 25.88% | Redeemed | 01/01/2017 | | | 1800 | 19.69% | Redeemed | Dec-16 | 0 | 1988 | 1988 | 21.75% | Issued | Nov-16 | 0 | 1595 | 1595 | 17.45% | Issued | Oct-16 | 0 | 1088 | 1088 | 11.90% | Issued | Sep-16 | 0 | 1712 | 1712 | 18.73% | Issued | Aug-16 | 0 | 1708 | 1708 | 18.69% | Issued | Jul-16 | 0 | 1122 | 1122 | 12.28% | Issued | Jul-16 | 0 | 1122 | 1122 | 12.28% | Issued | Jun-16 | 0 | 637 | 637 | 6.97% | Issued | May-16 | 0 | 1050 | 1050 | 11.49% | Issued | Apr-16 | 0 | 1383 | 1383 | 15.13% | Issued | Mar-16 | 0 | 1691 | 1691 | 18.50% | Redeemed | Feb-16 | 0 | 2305 | 2305 | 25.22% | Redeemed | Jan-16 | 0 | 2707 | 2707 | 29.62% | Redeemed | Dec-15 | 0 | 3772 | 3772 | 41.27% | Redeemed | Nov-15 | 0 | 3256 | 3256 | 35.62% | Redeemed | Oct-15 | 0 | 744 | 744 | 8.14% | Redeemed | Sep-15 | 0 | 844 | 844 | 9.23% | Redeemed | Aug-15 | 0 | 1214 | 1214 | 13.28% | Redeemed | Jul-15 | 1611 | 1611 | 1611 | 17.63% | Redeemed | Jun-15 | 1298 | 1298 | 1298 | 14.20% | Redeemed | May-15 | 2330 | 2330 | 2330 | 25.49% | Redeemed | Apr-15 | 1512 | 1512 | 1512 | 16.54% | Redeemed | Mar-15 | 2614 | 2614 | 2614 | 28.60% | Redeemed | Feb-15 | 1847 | 1847 | 1847 | 20.21% | Redeemed | Jan-15 | 3602 | 3602 | 3602 | 39.41% | Redeemed | Dec-14 | 3201 | 3201 | 3201 | 35.02% | Redeemed | Nov-14 | 1387 | 1388 | 1388 | 15.19% | Redeemed | Oct-14 | 2478 | 2478 | 2478 | 27.11% | Redeemed | Sep-14 | 468 | 468 | 468 | 5.12% | Redeemed | Aug-14 | 1890 | 1890 | 1890 | 20.68% | Redeemed | Jul-14 | 877 | 878 | 878 | 9.61% | Redeemed | Jun-14 | 477 | 476 | 476 | 5.21% | Redeemed | May-14 | 1307 | 1308 | 1308 | 14.31% | Redeemed | Apr-14 | 1186 | 1186 | 1186 | 12.98% | Redeemed | Mar-14 | 2103 | 2103 | 2103 | 23.01% | Redeemed | Feb-14 | 3054 | 3054 | 3054 | 33.41% | Redeemed | Jan-14 | 2682 | 2683 | 2682 | 29.34% | Redeemed | Dec-13 | 3563 | 3563 | 3563 | 38.98% | Expired | Nov-13 | 1532 | 1532 | 1532 | 16.76% | Redeemed | Oct-13 | 2239 | 2239 | 1 | 0.01% | Redeemed | Sep-13 | 1194 | 1194 | 1194 | 13.06% | Redeemed | Aug-13 | 1180 | 1181 | 1181 | 12.92% | Redeemed | Jul-13 | 614 | 616 | 616 | 6.74% | Redeemed | Jun-13 | 1245 | 1245 | 1245 | 13.62% | Redeemed | May-13 | 2253 | 2254 | 2254 | 24.66% | Redeemed | Apr-13 | 2325 | 2325 | 2325 | 25.44% | Redeemed | Mar-13 | 1748 | 1749 | 1749 | 19.14% | Redeemed | Feb-13 | 1452 | 1452 | 1452 | 15.89% | Redeemed | Jan-13 | 1966 | 1967 | 1967 | 21.52% | Redeemed | Dec-12 | 2510 | 2510 | 2510 | 27.46% | Redeemed | Nov-12 | 1864 | 1864 | 1864 | 20.39% | Redeemed | Oct-12 | 1413 | 1414 | 1414 | 15.47% | Redeemed | Sep-12 | 1924 | 1925 | 1925 | 21.06% | Redeemed | Aug-12 | 1170 | 1171 | 1171 | 12.81% | Redeemed | Jul-12 | 925 | 926 | 926 | 10.13% | Redeemed | Jun-12 | 1663 | 1663 | 1663 | 18.19% | Redeemed | May-12 | 1242 | 1243 | 1243 | 13.60% | Redeemed | Apr-12 | 1543 | 1544 | 1544 | 16.89% | Redeemed | Mar-12 | 1228 | 1228 | 1228 | 13.44% | Redeemed | Feb-12 | 1961 | 1962 | 1962 | 21.47% | Redeemed | Jan-12 | 3111 | 3111 | 3111 | 34.04% | Redeemed | Dec-11 | 4063 | 4063 | 4063 | 44.45% | Redeemed | Nov-11 | 2119 | 2119 | 2119 | 23.18% | Redeemed | Oct-11 | 2920 | 2920 | 2920 | 31.95% | Redeemed | Sep-11 | 2426 | 2426 | 2426 | 26.54% | Redeemed | Aug-11 | 1098 | 1099 | 1099 | 12.02% | Redeemed | Jul-11 | 739 | 740 | 740 | 8.10% | Redeemed | Jun-11 | 1274 | 1274 | 1274 | 13.94% | Redeemed | May-11 | 2751 | 2752 | 2752 | 30.11% | Redeemed | Apr-11 | 1238 | 1238 | 1238 | 13.54% | Redeemed | Mar-11 | 1144 | 1146 | 1146 | 12.54% | Redeemed | Feb-11 | 2036 | 2037 | 2037 | 22.29% | Redeemed | Jan-11 | 1650 | 1651 | 1651 | 18.06% | Redeemed | Dec-10 | 716 | 717 | 717 | 7.84% | Redeemed | Nov-10 | 1879 | 1880 | 1880 | 20.57% | Redeemed |
|
Capacity: 16 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 31 m/s (69.347 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 11/24/2024 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Case Study - Medium Wind n 2016, Green Cat Renewable Developments Limited (GCRD) purchased the Deuchries Wind Farm project after the previous owner decided the project was no longer viable Source: greencat, Date and Time of entry: Friday, November 22, 2024 00:00
Little Crow Solar Park Little Crow Solar Park is in Lincolnshire and is situated 2.5km northwest of the village of Broughton and directly to the east of the British steelworks at Scunthorpe. Source: inrg, Date and Time of entry: Friday, November 22, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Monday, September 9, 2024 00:00
How many more wind turbines will the UK build?. The government says it wants to generate enough wind energy to be able to power every home in the UK by 2030. Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
|
|
©2017
Simon Mallett |
|