Loading
Page views this IP this session = 1 of 10 unsubscribed pagesDummuie Wind Farm
Click here for Generation Forecast for wind farms based on Met office data
Dummuie Wind Farm (Wind , Active) Location in the UK : Scotland, Aberdeenshire Type of installation: Wind on/offshore: on Turbines :7 Capacity : 10.4 MW Approx Date of 1st power generation: April 2007
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
The Dummuie Wind Farm, developed and built by Eco2, started operating in April 2007. Located in Huntly, Aberdeenshire, it is now owned by IKEA Energy Services Ltd with Eco2 providing operational services.
Model: |
Vestas V66
|
Start Speed: |
5
|
Capacity: |
2
|
Optimal Speed: |
15
|
Rotor Diameter: |
66
|
Stop Speed: |
25
|
Hub Height |
47 Avg for all turbines:47
|
Avg. Elevation: |
265
|
Web Page: |
|
Comment: |
|
East Mains Dummuie Drumblade Huntly Aberdeensh AB54 4RL Scotland
Relationship |
Company (For:
Dummuie
) |
Sorry I found no matches, Please try again.
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Dummuie 12.3 MW
|
Energy Type: |
Wind Onshore |
County: |
Grampian Country: Scotland LPA: Aberdeenshire Council
|
Site ID and Reference: |
3200 / N00211W
District:
|
Applicant: |
Tetro Energy Ltd (ECO2)
Application :
APP/2003/0084
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
7 |
Turbine Capacity: |
1.75 |
Height of Turbines: |
|
Calculated capacity: |
12.25 |
Site Address: |
East Dummuie
Huntly
|
|
|
County: |
Grampian Region: Scotland
|
OS Coordinates: |
358600 / 358600
|
Development Status: |
Operational
|
Application Submitted: |
8/20/2003
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
2/20/2004
|
Construction Date: |
6/1/2006
|
|
|
Generator Live |
1/1/2007
|
This Record Last Updated: |
6/4/2015
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
2/20/2004 |
Site Name: |
Dummuies Windfarm - A
|
Generator Type: |
On-shore wind (ROS code = SQ)
|
Scheme : |
RO
|
Generator ID: |
R00075SQSC
|
Capacity: |
12250
|
Status: |
Live
|
Accreditation Date: |
8/20/2003
|
|
|
Commission Date: |
1/1/2007
|
|
|
Applicant: |
Dummuies Windfarm Huntly Limited
|
Applicant Address: |
Vision House, Oak Tree Court
Mulberry Drive
Cardiff Gate Business Park
Cardiff
CF23 8RS
Wales
|
Address: |
Dummuies Windfarm - A (01.02.07)
East MainsDummuieDrumbladeHuntlyAberdeensh
AB54 4RL
Scotland
|
Capacity: 24.5 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 25 m/s (55.925 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 12/3/2024 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Case Study - Medium Wind n 2016, Green Cat Renewable Developments Limited (GCRD) purchased the Deuchries Wind Farm project after the previous owner decided the project was no longer viable Source: greencat, Date and Time of entry: Friday, November 22, 2024 00:00
Little Crow Solar Park Little Crow Solar Park is in Lincolnshire and is situated 2.5km northwest of the village of Broughton and directly to the east of the British steelworks at Scunthorpe. Source: inrg, Date and Time of entry: Friday, November 22, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Monday, September 9, 2024 00:00
How many more wind turbines will the UK build?. The government says it wants to generate enough wind energy to be able to power every home in the UK by 2030. Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
|
|
©2017
Simon Mallett |
|