Forss Wind Farm (Wind , Active) Location in the UK : Scotland, Highland Type of installation: Wind on/offshore: on Turbines :6 Capacity : 7.2 MW Approx Date of 1st power generation: May 2007
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
The existing turbines at the site were developed, built, and are owned and operated, by RES. The current 7.2 MW wind farm can provide enough clean green, renewable energy equivalent to the annual average consumption of over 3,700 homes in the Highland region. The additional turbines will provide the equivalent to the annual consumption of 3,000-5,000 homes*.
Abbey are putting together proposals to develop their former US Navy communications site at Forss, Caithness to promote the creation of an Energy and Data Park in an ambitious bid to consolidate the area's potential to be a national leader in the development of wind, wave and tidal renewable energy, and address the growing 21st century demand for secure data storage facilities.
Model: |
aa 2mw turbine
|
Start Speed: |
5
|
Capacity: |
2
|
Optimal Speed: |
15
|
Rotor Diameter: |
80
|
Stop Speed: |
25
|
Hub Height |
47 Avg for all turbines:47
|
Avg. Elevation: |
30
|
Web Page: |
|
Comment: |
For proposed projects where turbine yet to be agreed
|
Forss, Thurso, Caithness
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Hill of Lybster (Wind Turbine - Extension) 1.5 MW
|
Energy Type: |
Wind Onshore |
County: |
Highland Country: Scotland LPA: Highland Council
|
Site ID and Reference: |
5187 /
District:
|
Applicant: |
The Energy Workshop
Application :
17/04934/FUL
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
1 |
Turbine Capacity: |
1.5 |
Height of Turbines: |
100 |
Calculated capacity: |
1.5 |
Site Address: |
Land 200M N Of, 3 Lybster Road, Forss, Thurso, Highlands
|
|
KW14 7YA
|
County: |
Highland Region: Scotland
|
OS Coordinates: |
302481 / 302481
|
Development Status: |
Operational
|
Application Submitted: |
10/20/2017
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
8/16/2018
|
Construction Date: |
|
|
|
Generator Live |
4/12/2021
|
This Record Last Updated: |
10/2/2018
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
8/16/2018 |
Site Name: |
Forss Extension (Forss III) 6.5 MW
|
Energy Type: |
Wind Onshore |
County: |
Highland Country: Scotland LPA: Highland Council
|
Site ID and Reference: |
3783 / AA168
District:
|
Applicant: |
Renewable Energy Systems (RES)
Application :
10/04434/FUL
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
5 |
Turbine Capacity: |
1.3 |
Height of Turbines: |
|
Calculated capacity: |
6.5 |
Site Address: |
Thurso, Caithness
|
|
|
County: |
Highland Region: Scotland
|
OS Coordinates: |
302174 / 302174
|
Development Status: |
Appeal Refused
|
Application Submitted: |
10/28/2010
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
10/19/2011
|
Construction Date: |
|
|
|
Generator Live |
|
This Record Last Updated: |
1/2/2013
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
7/19/2012 |
Granted: |
|
Appeal Granted: |
10/19/2011 |
Site Name: |
Forss Wind Farm (Extension) 5.2 MW
|
Energy Type: |
Wind Onshore |
County: |
Highland Country: Scotland LPA: Highland Council
|
Site ID and Reference: |
4679 / N00065W
District:
|
Applicant: |
Renewable Energy Systems (RES)
Application :
01/00380/FULCA
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
4 |
Turbine Capacity: |
1.3 |
Height of Turbines: |
|
Calculated capacity: |
5.2 |
Site Address: |
Ex Navy Base Forss, Dounreay Thurso Caithness
|
|
KW14 7YB
|
County: |
Highland Region: Scotland
|
OS Coordinates: |
302000 / 302000
|
Development Status: |
Operational
|
Application Submitted: |
1/5/2005
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
1/1/2007
|
|
|
Generator Live |
7/1/2007
|
This Record Last Updated: |
5/10/2016
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Forss Wind Farm 2.6 MW
|
Energy Type: |
Wind Onshore |
County: |
Highland Country: Scotland LPA: Highland Council
|
Site ID and Reference: |
6636 /
District:
|
Applicant: |
Renewable Energy Systems (RES)
Application :
01/00030/FULCA
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
2 |
Turbine Capacity: |
1.3 |
Height of Turbines: |
99 |
Calculated capacity: |
2.6 |
Site Address: |
Wind Turbine Ex Navy Base Forss Dounreay Thurso Caithness
|
|
KW14 7YB
|
County: |
Highland Region: Scotland
|
OS Coordinates: |
302000 / 302000
|
Development Status: |
Operational
|
Application Submitted: |
1/12/2001
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
1/1/2003
|
|
|
Generator Live |
7/1/2003
|
This Record Last Updated: |
6/4/2018
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Hill of Lybster 4.9 MW
|
Energy Type: |
Wind Onshore |
County: |
Highland Country: Scotland LPA: Highland Council
|
Site ID and Reference: |
3309 / S0036W3
District:
|
Applicant: |
Fivestone Ltd (subsidiary of Abbey Produce)
Application :
CA2001030
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
4 |
Turbine Capacity: |
1.3 |
Height of Turbines: |
|
Calculated capacity: |
5.2 |
Site Address: |
Forss Phase 2, Caithness
|
|
|
County: |
Highland Region: Scotland
|
OS Coordinates: |
302000 / 302000
|
Development Status: |
Operational
|
Application Submitted: |
4/28/2000
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
|
|
|
Generator Live |
2/8/2003
|
This Record Last Updated: |
6/9/2010
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Forss Wind Farm Phase 2
|
Generator Type: |
On-shore wind (ROS code = SQ)
|
Scheme : |
RO
|
Generator ID: |
R00068SQSC
|
Capacity: |
4999
|
Status: |
Live
|
Accreditation Date: |
4/28/2000
|
|
|
Commission Date: |
5/1/2007
|
|
|
Applicant: |
RES Ltd
|
Applicant Address: |
Beaufort Court
Egg Farm Lane
Kings Langley
WD4 8LR
England
|
Address: |
Forss Wind Farm Phase 2
Forss Wind FarmEx US Navy communications BaseF
Scotland
|
Site Name: |
Forss Wind Farm Phase 2
|
Generator Type: |
Wind
|
Scheme : |
REGO
|
Generator ID: |
G01127NWSC
|
Capacity: |
4999
|
Status: |
Live
|
Accreditation Date: |
4/28/2000
|
|
|
Commission Date: |
5/1/2007
|
|
|
Applicant: |
RES Ltd
|
Applicant Address: |
Beaufort Court
Egg Farm Lane
Kings Langley
WD4 8LR
England
|
Address: |
Forss Wind Farm Phase 2
Forss Wind FarmEx US Navy communications BaseF
Scotland
|
|
Assumptions: Capacity: 4999kW 4.999 MW, Thus over the month Capacity * 720 hours per month = 3599.28 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/03/2018 | | | 1710 | 34.21% | Issued | 01/02/2018 | | | 1531 | 30.63% | Issued | 01/01/2018 | | | 1863 | 37.27% | Issued | 01/12/2017 | | | 1215 | 24.30% | Issued | 01/12/2017 | | | 697 | 13.94% | Issued | 01/11/2017 | | | 2428 | 48.57% | Issued | 01/10/2017 | | | 1857 | 37.15% | Issued | 01/09/2017 | | | 1134 | 22.68% | Issued | 01/08/2017 | | | 967 | 19.34% | Issued | 01/07/2017 | | | 918 | 18.36% | Issued | 01/06/2017 | | | 1163 | 23.26% | Issued | 01/05/2017 | | | 1076 | 21.52% | Issued | 01/04/2017 | | | 2050 | 41.01% | Issued | 01/03/2017 | | | 1501 | 30.03% | Redeemed | 01/02/2017 | | | 1592 | 31.85% | Redeemed | 01/01/2017 | | | 1816 | 36.33% | Redeemed | Dec-16 | 0 | 1816 | 1816 | 36.33% | Issued | Nov-16 | 0 | 1672 | 1672 | 33.45% | Issued | Oct-16 | 0 | 1265 | 1265 | 25.31% | Issued | Sep-16 | 0 | 1187 | 1187 | 23.74% | Issued | Aug-16 | 0 | 1127 | 1127 | 22.54% | Issued | Jul-16 | 0 | 817 | 817 | 16.34% | Issued | Jun-16 | 0 | 786 | 786 | 15.72% | Issued | Jun-16 | 0 | 786 | 786 | 15.72% | Issued | May-16 | 0 | 973 | 973 | 19.46% | Issued | Apr-16 | 0 | 1580 | 1580 | 31.61% | Issued | Mar-16 | 0 | 1237 | 1237 | 24.74% | Redeemed | Feb-16 | 0 | 1834 | 1834 | 36.69% | Redeemed | Jan-16 | 0 | 2048 | 1328 | 26.57% | Redeemed | Dec-15 | 0 | 2163 | 2163 | 43.27% | Redeemed | Nov-15 | 0 | 1877 | 1877 | 37.55% | Redeemed | Oct-15 | 0 | 1328 | 1328 | 26.57% | Redeemed | Sep-15 | 0 | 1060 | 1060 | 21.20% | Redeemed | Aug-15 | 0 | 725 | 725 | 14.50% | Redeemed | Jul-15 | 808 | 808 | 808 | 16.16% | Redeemed | Jun-15 | 808 | 808 | 808 | 16.16% | Redeemed | May-15 | 1234 | 1235 | 1235 | 24.70% | Redeemed | Apr-15 | 708 | 703 | 707 | 14.14% | Redeemed | Mar-15 | 939 | 939 | 939 | 18.78% | Redeemed | Feb-15 | 1076 | 1076 | 1076 | 21.52% | Redeemed | Jan-15 | 1129 | 1129 | 1129 | 22.58% | Redeemed | Dec-14 | 1041 | 1041 | 1041 | 20.82% | Redeemed | Nov-14 | 1457 | 1457 | 1457 | 29.15% | Redeemed | Oct-14 | 1700 | 1700 | 1700 | 34.01% | Redeemed | Sep-14 | 851 | 846 | 851 | 17.02% | Redeemed | Aug-14 | 1494 | 1494 | 1494 | 29.89% | Redeemed | Jul-14 | 777 | 771 | 777 | 15.54% | Redeemed | Jun-14 | 576 | 570 | 575 | 11.50% | Redeemed | May-14 | 751 | 746 | 752 | 15.04% | Redeemed | Apr-14 | 1449 | 1449 | 1449 | 28.99% | Redeemed | Mar-14 | 1929 | 1929 | 1929 | 38.59% | Redeemed | Feb-14 | 2005 | 2006 | 2006 | 40.13% | Redeemed | Jan-14 | 1611 | 1611 | 1611 | 32.23% | Redeemed | Dec-13 | 2343 | 2343 | 2342 | 46.85% | Redeemed | Nov-13 | 2159 | 2159 | 2159 | 43.19% | Redeemed | Oct-13 | 1435 | 1434 | 65 | 1.30% | Revoked | Sep-13 | 1373 | 1374 | 1 | 0.02% | Redeemed | Aug-13 | 945 | 940 | 945 | 18.90% | Redeemed | Jul-13 | 903 | 897 | 903 | 18.06% | Redeemed | Jun-13 | 515 | 509 | 515 | 10.30% | Redeemed | May-13 | 1262 | 1262 | 1262 | 25.25% | Redeemed | Apr-13 | 1448 | 1448 | 1448 | 28.97% | Redeemed | Mar-13 | 1395 | 1395 | 1395 | 27.91% | Redeemed | Feb-13 | 1341 | 1340 | 1340 | 26.81% | Redeemed | Jan-13 | 1805 | 1806 | 1806 | 36.13% | Redeemed | Dec-12 | 1928 | 1928 | 1928 | 38.57% | Redeemed | Nov-12 | 1572 | 1571 | 1571 | 31.43% | Redeemed | Oct-12 | 1499 | 1499 | 1499 | 29.99% | Redeemed | Sep-12 | 2030 | 2031 | 2031 | 40.63% | Redeemed | Aug-12 | 680 | 675 | 680 | 13.60% | Redeemed | Jul-12 | 664 | 660 | 664 | 13.28% | Redeemed | Jun-12 | 994 | 994 | 994 | 19.88% | Redeemed | May-12 | 1177 | 1177 | 1177 | 23.54% | Redeemed | Apr-12 | 1195 | 1195 | 1195 | 23.90% | Redeemed | Mar-12 | 1814 | 1814 | 1814 | 36.29% | Redeemed | Feb-12 | 2014 | 2014 | 2014 | 40.29% | Redeemed | Jan-12 | 2174 | 2174 | 2174 | 43.49% | Redeemed | Dec-11 | 2158 | 2158 | 2158 | 43.17% | Redeemed | Nov-11 | 2078 | 2078 | 2078 | 41.57% | Redeemed | Oct-11 | 2067 | 2067 | 2067 | 41.35% | Redeemed | Sep-11 | 1416 | 1416 | 1416 | 28.33% | Redeemed | Aug-11 | 1183 | 1183 | 1183 | 23.66% | Redeemed | Jul-11 | 1012 | 1012 | 1012 | 20.24% | Redeemed | Jun-11 | 731 | 731 | 731 | 14.62% | Redeemed | May-11 | 1773 | 1773 | 1773 | 35.47% | Redeemed | Apr-11 | 1382 | 1382 | 1382 | 27.65% | Redeemed | Mar-11 | 1646 | 1646 | 1646 | 32.93% | Redeemed | Feb-11 | 1929 | 1929 | 1929 | 38.59% | Redeemed | Jan-11 | 1766 | 1766 | 1766 | 35.33% | Redeemed | Dec-10 | 1471 | 1471 | 1471 | 29.43% | Redeemed | Nov-10 | 1510 | 1510 | 1510 | 30.21% | Redeemed | Oct-10 | 2048 | 2048 | 2048 | 40.97% | Redeemed |
|
Capacity: 19.96 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 25 m/s (55.925 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 2/3/2025 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
FORSS Energy Park
RES: FORSS Wind Fram Extension
Highland councillors refuse wind turbines at FORSS Highland Council's planning review body has opposed a planned extension to a wind farm on a former Cold War base.
Wind farm 'would affect Wick airport' The other farms are at FORSS, Causeymire, Boulfruich, Flexhill, Achairn, Baillie, Camster, Bettyhill, Strathy North, Strathy South, South Shebster, Hill of Lieurary, Burn of Whilk, Stroupster, Bower, Durran, Olgrinmore, Halsary and Wathegar.
|
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017
Simon Mallett |
|