Page views this IP this session = 1 of 10 unsubscribed pagesLynemouth Biomass Energy
Lynemouth (Biomass , Active) Location in the UK : England, Northumberland Type of installation: Biomass on/offshore: on Turbines :0 Capacity : 420 MW Approx Date of 1st power generation: 21/11/2018
/YES
As of February 2014, biomass conversion is still intended to go ahead: The RES Group is looking to build a £350m biomass power station there, and another scheme involves Lynemouth Power Station, which aims to convert to biomass by 2015.
This is a unique UK Power station which is undergoing a sale process from Alcan to Curen, a subsidiary of RWE. Because this was/ is a dedicated coal fired station that was used for aluminium smelting it does not necessarily conform to regulations, for supplying the National Grid. The new owners want to convert it to a biomass plant as detailed in the summary of an exemption application that would allow the station to remain open.
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Lynemouth Power Station 420 MW
|
Energy Type: |
Biomass (dedicated) |
County: |
Northumberland Country: England LPA: Northumberland County Council
|
Site ID and Reference: |
115 / AA430
District:
|
Applicant: |
Lynemouth Power
Application :
|
(Go to search to find Application) |
Site Address: |
Woodhorn Ashington Northumberland
|
|
NE63 9YH
|
County: |
Northumberland Region: North East
|
OS Coordinates: |
429850 / 429850
|
Development Status: |
Operational
|
Application Submitted: |
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
1/1/2016
|
|
|
Generator Live |
11/21/2018
|
This Record Last Updated: |
11/21/2018
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Alcan Lynemouth Power Station
|
Generator Type: |
Biodegradable (REGO code = MW)
|
Scheme : |
REGO
|
Generator ID: |
G00676MWEN
|
Capacity: |
396000
|
Status: |
Live
|
Accreditation Date: |
|
|
|
Commission Date: |
5/1/2003
|
|
|
Applicant: |
Lynemouth Power Station
|
Applicant Address: |
Lynemouth Power Station
ASHINGTON
NE63 9NW
England
|
Address: |
Alcan Lynemouth Power Station
Alcan Smelting and Power UK - B
C
DLynemouth Works Power StationAshingtonNorth
NE63 9NW
England
|
|
Assumptions: Capacity: 396000kW 396 MW, Thus over the month Capacity * 720 hours per month = 285120 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
Nov-13 | 547 | 164 | 582 | 0.15% | Expired | Oct-13 | 1178 | 354 | 1254 | 0.32% | Expired | May-13 | 67 | 20 | 71 | 0.02% | Expired | Apr-13 | 1422 | 427 | 1518 | 0.38% | Expired | Mar-13 | 753 | 377 | 804 | 0.20% | Expired | Aug-11 | 12168 | 6084 | 12909 | 3.26% | Expired | Jul-11 | 2249 | 1124 | 228 | 0.06% | Redeemed | Jun-11 | 711 | 355 | 633 | 0.16% | Expired | May-11 | 635 | 318 | 105 | 0.03% | Redeemed | Apr-11 | 303 | 152 | 263 | 0.07% | Expired | Dec-10 | 466 | 233 | 492 | 0.12% | Expired | Nov-10 | 4484 | 2242 | 1202 | 0.30% | Redeemed | Oct-10 | 2523 | 1261 | 2004 | 0.51% | Expired |
|
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Monday, September 9, 2024 00:00
How many more wind turbines will the UK build?. The government says it wants to generate enough wind energy to be able to power every home in the UK by 2030. Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Nine offshore wind farm projects awarded in UK auction The new offshore projects include what will be Europe's largest and second-largest wind farms, Hornsea 3 and Hornsea 4, which will be built off the Yorkshire coast by Ørsted Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Carn Nicholas Drone footage Date and Time of entry: Tuesday, March 19, 2024 00:00
|
|
©2017
Simon Mallett |
|