Harlock Hill Wind Farm (Wind , Closed) Location in the UK : England, Cumbria Type of installation: Wind on/offshore: on Turbines :5 Capacity : 2.5 MW Approx Date of 1st power generation: January 1997
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
Also see Furness WInd Farm The first share offer in 1996/97 raised 1.2 million to buy two turbines at the Harlock Hill wind farm. In 1998/99 the second share offer raised a further 670,000 to buy one turbine at the Haverigg II wind farm site. Preference was shown for local investors, so that the community shares the economic benefits from their local wind farm. Around 40% of existing Baywind shareholders live either in Cumbria or North Lancashire with a wider number from the Northwest Region.
Model: |
Wind World W3700/500
|
Start Speed: |
0
|
Capacity: |
0.5
|
Optimal Speed: |
0
|
Rotor Diameter: |
37
|
Stop Speed: |
0
|
Hub Height |
40 Avg for all turbines:
|
Avg. Elevation: |
|
Web Page: |
|
Comment: |
|
Harlock Hill Pennington Ulverston LA12 7SA England
Relationship |
Company (For:
Harlock Hill
) |
Sorry I found no matches, Please try again.
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Harlock Hill Wind Farm 2.5 MW
|
Energy Type: |
Wind Onshore |
County: |
Cumbria Country: England LPA: South Lakeland District Council
|
Site ID and Reference: |
2617 / 07056W3
District:
|
Applicant: |
The Wind Company
Application :
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
5 |
Turbine Capacity: |
0.5 |
Height of Turbines: |
|
Calculated capacity: |
2.5 |
Site Address: |
Harlock Hill Wind Farm
, Pennington
, Near Ulverston
, Cumbria
|
|
LA12 0
|
County: |
Cumbria Region: North West
|
OS Coordinates: |
325300 / 325300
|
Development Status: |
Operational
|
Application Submitted: |
2/3/1995
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
|
|
|
Generator Live |
1/1/1997
|
This Record Last Updated: |
8/1/2016
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Harlock Hill Wind Farm
|
Generator Type: |
On-shore wind (RO code = RQ)
|
Scheme : |
RO
|
Generator ID: |
R00395RQEN
|
Capacity: |
4560
|
Status: |
Live
|
Accreditation Date: |
2/3/1995
|
|
|
Commission Date: |
6/1/2016
|
|
|
Applicant: |
High Winds Community Energy Society
|
Applicant Address: |
Energy 4 All
Unit 26
Barrow-in-Furness
LA14 2PN
England
|
Address: |
Harlock Hill
Pennington
Near Ulverston
LA12 7SB
England
|
Site Name: |
Harlock Hill Wind Farm
|
Generator Type: |
Wind
|
Scheme : |
REGO
|
Generator ID: |
G02943NWEN
|
Capacity: |
4560
|
Status: |
Live
|
Accreditation Date: |
2/3/1995
|
|
|
Commission Date: |
6/1/2016
|
|
|
Applicant: |
High Winds Community Energy Society
|
Applicant Address: |
Energy 4 All
Unit 26
Barrow-in-Furness
LA14 2PN
England
|
Address: |
Harlock Hill
Pennington
Near Ulverston
LA12 7SB
England
|
|
Assumptions: Capacity: 4560kW 4.56 MW, Thus over the month Capacity * 720 hours per month = 3283.2 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/04/2018 | | | 802 | 17.59% | Issued | 01/03/2018 | | | 1246 | 27.32% | Issued | 01/02/2018 | | | 983 | 21.56% | Issued | 01/01/2018 | | | 1680 | 36.84% | Issued | 01/12/2017 | | | 1216 | 26.67% | Issued | 01/11/2017 | | | 1151 | 25.24% | Issued | 01/10/2017 | | | 1584 | 34.74% | Issued | 01/09/2017 | | | 817 | 17.92% | Issued | 01/09/2017 | | | 26 | 0.57% | Issued | 01/08/2017 | | | 104 | 2.28% | Issued | 01/08/2017 | | | 631 | 13.84% | Issued | 01/07/2017 | | | 721 | 15.81% | Issued | 01/06/2017 | | | 755 | 16.56% | Issued | 01/05/2017 | | | 702 | 15.39% | Issued | 01/04/2017 | | | 834 | 18.29% | Issued | 01/03/2017 | | | 928 | 20.35% | Redeemed | 01/02/2017 | | | 1247 | 27.35% | Redeemed | 01/01/2017 | | | 879 | 19.28% | Redeemed | Dec-16 | 0 | 946 | 1052 | 23.07% | Issued | Nov-16 | 0 | 684 | 760 | 16.67% | Issued | Oct-16 | 0 | 666 | 740 | 16.23% | Issued | Sep-16 | 0 | 373 | 414 | 9.08% | Issued | Aug-16 | 0 | 357 | 397 | 8.71% | Issued | Jul-16 | 0 | 331 | 367 | 8.05% | Issued | Jun-16 | 0 | 95 | 108 | 2.37% | Issued |
|
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017
Simon Mallett |
|