Alltwalis Wind Farm (Wind , Active) Location in the UK : Wales, Carmarthenshire, Pencader Type of installation: Wind on/offshore: on Turbines :10 Capacity : 23 MW Approx Date of 1st power generation: January 2010
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
(Blaengwen) After receiving planning permission from Carmarthenshire County Council, construction was completed in January 2010 on a 10-turbine wind farm on farmland north east of Alltwalis, 12km north of Carmarthen. The wind farm, which is now owned and operated by Statkraft is generating clean electricity for more than 16,770 homes. The grassland site continues to be used for the grazing of sheep and cattle
Model: |
Siemens SWT 2.3
|
Start Speed: |
4.5
|
Capacity: |
2.3
|
Optimal Speed: |
25
|
Rotor Diameter: |
101
|
Stop Speed: |
25
|
Hub Height |
65 Avg for all turbines:65
|
Avg. Elevation: |
316
|
Web Page: |
http://tinyurl.com/simens2-3 |
Comment: |
|
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Blaengwen 23 MW
|
Energy Type: |
Wind Onshore |
County: |
Dyfed Country: Wales LPA: Carmarthenshire County Council
|
Site ID and Reference: |
4670 / EN00358
District:
|
Applicant: |
Statkraft and Catamount Energy Corporation
Application :
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
10 |
Turbine Capacity: |
2.2999999999999998 |
Height of Turbines: |
|
Calculated capacity: |
23 |
Site Address: |
Pencader Carms.
|
|
SA39 94P
|
County: |
Dyfed Region: Wales
|
OS Coordinates: |
246387 / 246387
|
Development Status: |
Operational
|
Application Submitted: |
7/6/2006
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
11/1/2008
|
|
|
Generator Live |
11/30/2009
|
This Record Last Updated: |
4/6/2010
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Blaengwen Farm 30.2 MW
|
Energy Type: |
Wind Onshore |
County: |
Dyfed Country: Wales LPA: Carmarthenshire County Council
|
Site ID and Reference: |
3289 / N00545W
District:
|
Applicant: |
CATAMOUNT CYMRU CYF (agent ENTEC UK Ltd) Force 9 Energy
Application :
W/09205
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
10 |
Turbine Capacity: |
3 |
Height of Turbines: |
|
Calculated capacity: |
30 |
Site Address: |
Pencader
, Carms.
|
|
SA39 94P
|
County: |
Dyfed Region: Wales
|
OS Coordinates: |
246387 / 246387
|
Development Status: |
Revised
|
Application Submitted: |
1/27/2005
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
11/24/2005
|
Construction Date: |
|
|
|
Generator Live |
|
This Record Last Updated: |
10/27/2005
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
11/24/2005 |
Site Name: |
Alltwalis Wind Farm
|
Generator Type: |
On-shore wind (RO code = RQ)
|
Scheme : |
RO
|
Generator ID: |
R00191RQWA
|
Capacity: |
23000
|
Status: |
Live
|
Accreditation Date: |
1/27/2005
|
|
|
Commission Date: |
9/21/2009
|
|
|
Applicant: |
Statkraft Wind UK Ltd.
|
Applicant Address: |
26-28 Hammersmith Grove
London
W6 7BA
England
|
Address: |
Alltwalis Wind Farm
The old concrete works
Alltwalis
SA32 7EE
Wales
|
Site Name: |
Alltwalis Wind Farm
|
Generator Type: |
Wind
|
Scheme : |
REGO
|
Generator ID: |
G01342NWWA
|
Capacity: |
23000
|
Status: |
Live
|
Accreditation Date: |
1/27/2005
|
|
|
Commission Date: |
9/21/2009
|
|
|
Applicant: |
Statkraft Wind UK Ltd.
|
Applicant Address: |
26-28 Hammersmith Grove
London
W6 7BA
England
|
Address: |
Alltwalis Wind Farm
The old concrete works
Alltwalis
SA32 7EE
Wales
|
|
Assumptions: Capacity: 23000kW 23 MW, Thus over the month Capacity * 720 hours per month = 16560 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/04/2018 | | | 4359 | 18.95% | Issued | 01/03/2018 | | | 5734 | 24.93% | Issued | 01/02/2018 | | | 3153 | 13.71% | Issued | 01/02/2018 | | | 3030 | 13.17% | Issued | 01/01/2018 | | | 4138 | 17.99% | Issued | 01/01/2018 | | | 4307 | 18.73% | Issued | 01/12/2017 | | | 3180 | 13.83% | Issued | 01/12/2017 | | | 50 | 0.22% | Retired | 01/12/2017 | | | 3103 | 13.49% | Retired | 01/11/2017 | | | 2247 | 9.77% | Retired | 01/11/2017 | | | 2159 | 9.39% | Retired | 01/10/2017 | | | 3275 | 14.24% | Retired | 01/10/2017 | | | 3147 | 13.68% | Retired | 01/09/2017 | | | 2408 | 10.47% | Retired | 01/09/2017 | | | 2507 | 10.90% | Retired | 01/08/2017 | | | 1589 | 6.91% | Issued | 01/08/2017 | | | 1526 | 6.63% | Issued | 01/07/2017 | | | 549 | 2.39% | Issued | 01/07/2017 | | | 571 | 2.48% | Issued | 01/06/2017 | | | 2013 | 8.75% | Retired | 01/06/2017 | | | 1935 | 8.41% | Retired | 01/05/2017 | | | 1783 | 7.75% | Issued | 01/05/2017 | | | 1855 | 8.07% | Issued | 01/04/2017 | | | 1713 | 7.45% | Issued | 01/04/2017 | | | 1783 | 7.75% | Issued | 01/03/2017 | | | 3360 | 14.61% | Issued | 01/03/2017 | | | 3498 | 15.21% | Issued | 01/02/2017 | | | 3354 | 14.58% | Issued | 01/02/2017 | | | 3223 | 14.01% | Issued | 01/01/2017 | | | 2937 | 12.77% | Issued | 01/01/2017 | | | 2822 | 12.27% | Issued | Dec-16 | 0 | 6119 | 2998 | 13.03% | Pending Tr | Nov-16 | 0 | 4418 | 2253 | 9.80% | Pending Tr | Oct-16 | 0 | 4139 | 2111 | 9.18% | Pending Tr | Sep-16 | 0 | 4689 | 2391 | 10.40% | Pending Tr | Aug-16 | 0 | 3740 | 1833 | 7.97% | Pending Tr | Jul-16 | 0 | 3281 | 1608 | 6.99% | Pending Tr | Jul-16 | 0 | 3281 | 1608 | 6.99% | Pending Tr | Jun-16 | 0 | 1981 | 1020 | 4.43% | Pending Tr | May-16 | 0 | 3279 | 1607 | 6.99% | Pending Tr | Apr-16 | 0 | 4174 | 2129 | 9.26% | Pending Tr | Mar-16 | 0 | 4102 | 2092 | 9.10% | Redeemed | Feb-16 | 0 | 5843 | 2980 | 12.96% | Redeemed | Jan-16 | 0 | 7765 | 3805 | 16.54% | Redeemed | Dec-15 | 0 | 10369 | 5288 | 22.99% | Redeemed | Nov-15 | 0 | 7660 | 3907 | 16.99% | Redeemed | Oct-15 | 0 | 3893 | 1908 | 8.30% | Redeemed | Sep-15 | 0 | 3288 | 1677 | 7.29% | Redeemed | Aug-15 | 0 | 2272 | 1174 | 5.10% | Redeemed | Jul-15 | 3581 | 3558 | 1826 | 7.94% | Redeemed | Jun-15 | 3861 | 3861 | 1969 | 8.56% | Redeemed | May-15 | 5311 | 5311 | 2602 | 11.31% | Redeemed | Apr-15 | 3851 | 3851 | 1964 | 8.54% | Redeemed | Mar-15 | 5786 | 5785 | 2950 | 12.83% | Redeemed | Feb-15 | 4571 | 4571 | 196 | 0.85% | Redeemed | Jan-15 | 6836 | 6837 | 3486 | 15.16% | Redeemed | Dec-14 | 6984 | 6984 | 6984 | 30.37% | Redeemed | Nov-14 | 5485 | 5485 | 5485 | 23.85% | Redeemed | Oct-14 | 6494 | 6494 | 6494 | 28.23% | Redeemed | Sep-14 | 2215 | 2197 | 1 | 0.00% | Redeemed | Aug-14 | 3936 | 3935 | 3935 | 17.11% | Redeemed | Jul-14 | 1303 | 1231 | 1303 | 5.67% | Redeemed | Jun-14 | 2176 | 2156 | 2176 | 9.46% | Redeemed | May-14 | 3374 | 3374 | 3374 | 14.67% | Redeemed | Apr-14 | 3670 | 3670 | 3670 | 15.96% | Redeemed | Mar-14 | 5501 | 5502 | 5502 | 23.92% | Redeemed | Feb-14 | 6996 | 6995 | 6995 | 30.41% | Redeemed | Jan-14 | 5868 | 5869 | 1 | 0.00% | Redeemed | Dec-13 | 5985 | 5990 | 5 | 0.02% | Redeemed | Nov-13 | 4170 | 4184 | 4183 | 18.19% | Redeemed | Oct-13 | 6305 | 6308 | 6308 | 27.43% | Redeemed | Sep-13 | 3988 | 4003 | 15 | 0.07% | Redeemed | Aug-13 | 2786 | 2786 | 2786 | 12.11% | Redeemed | Jul-13 | 2098 | 2098 | 2098 | 9.12% | Redeemed | Jun-13 | 4468 | 4478 | 10 | 0.04% | Redeemed | May-13 | 5683 | 5698 | 15 | 0.07% | Redeemed | Apr-13 | 6296 | 6301 | 6296 | 27.37% | Redeemed | Mar-13 | 5473 | 5484 | 5484 | 23.84% | Retired | Feb-13 | 5616 | 5620 | 5620 | 24.43% | Redeemed | Jan-13 | 5124 | 5124 | 5176 | 22.50% | Redeemed | Dec-12 | 6628 | 6634 | 6634 | 28.84% | Redeemed | Nov-12 | 4631 | 4646 | 4646 | 20.20% | Redeemed | Oct-12 | 4882 | 4889 | 7 | 0.03% | Redeemed | Sep-12 | 3838 | 3848 | 2448 | 10.64% | Redeemed | Aug-12 | 3169 | 3169 | 54 | 0.23% | Redeemed | Jul-12 | 1890 | 1890 | 13 | 0.06% | Redeemed | Jun-12 | 4431 | 4432 | 4431 | 19.27% | Redeemed | May-12 | 2211 | 2211 | 47 | 0.20% | Redeemed | Apr-12 | 4812 | 4819 | 7 | 0.03% | Redeemed | Mar-12 | 4148 | 4170 | 4170 | 18.13% | Redeemed | Feb-12 | 4534 | 4543 | 4543 | 19.75% | Redeemed | Jan-12 | 7543 | 7545 | 7545 | 32.80% | Redeemed | Dec-11 | 8605 | 8605 | 8605 | 37.41% | Redeemed | Nov-11 | 7920 | 7920 | 7920 | 34.43% | Redeemed | Oct-11 | 6867 | 6872 | 6872 | 29.88% | Redeemed | Sep-11 | 3995 | 4035 | 4035 | 17.54% | Redeemed | Aug-11 | 2349 | 2315 | 1686 | 7.33% | Revoked | Jul-11 | 2787 | 2809 | 2809 | 12.21% | Redeemed | Jun-11 | 2639 | 2679 | 2679 | 11.65% | Redeemed | May-11 | 6421 | 6438 | 6438 | 27.99% | Redeemed | Apr-11 | 4022 | 4035 | 4035 | 17.54% | Redeemed | Mar-11 | 5091 | 5091 | 5091 | 22.13% | Redeemed | Feb-11 | 6537 | 6537 | 6537 | 28.42% | Redeemed | Jan-11 | 4623 | 4623 | 2490 | 10.83% | Redeemed | Dec-10 | 3956 | 3956 | 3956 | 17.20% | Redeemed | Nov-10 | 4906 | 4906 | 4906 | 21.33% | Redeemed | Oct-10 | 5583 | 5583 | 5583 | 24.27% | Redeemed |
|
Capacity: 46 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 25 m/s (55.925 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 11/21/2024 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Monday, September 9, 2024 00:00
How many more wind turbines will the UK build?. The government says it wants to generate enough wind energy to be able to power every home in the UK by 2030. Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Nine offshore wind farm projects awarded in UK auction The new offshore projects include what will be Europe's largest and second-largest wind farms, Hornsea 3 and Hornsea 4, which will be built off the Yorkshire coast by Ørsted Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Carn Nicholas Drone footage Date and Time of entry: Tuesday, March 19, 2024 00:00
|
|
©2017
Simon Mallett |
|