Loading
Page views this IP this session = 2 of 10 unsubscribed pagesThe Hollies Wind Farm
Click here for Generation Forecast for wind farms based on Met office data
The Hollies Wind Farm (Wind , Active) Location in the UK : England, burgh le marsh, lincolnshire Type of installation: Wind on/offshore: on Turbines :2 Capacity : 2.6 MW Approx Date of 1st power generation: July 2008
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
Now fully operational both turbines produce enough green energy to meet the equivalent annual electricity needs of some 1,300 homes each year. With a tip height of 91 metres, the turbines are capable of generating 1.3 megawatts each giving the site a maximum combined power of up to 2.6 megawatts.
Model: |
Nordex N60/1300
|
Start Speed: |
4.5
|
Capacity: |
1.3
|
Optimal Speed: |
10
|
Rotor Diameter: |
60
|
Stop Speed: |
25
|
Hub Height |
0 Avg for all turbines:60
|
Avg. Elevation: |
3
|
Web Page: |
http://www.nordex-online.com/fileadmin/MEDIA/Produktinfos/EN/Nordex_N60_EN.pdf |
Comment: |
|
The Hollies Wind FarmHigh LaneCroft PE24 4SH England
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
The Hollies 2.6 MW
|
Energy Type: |
Wind Onshore |
County: |
Lincolnshire Country: England LPA: East Lindsey District Council
|
Site ID and Reference: |
3186 / N00179W
District:
|
Applicant: |
National Wind Power
Application :
S/039/711/02
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
2 |
Turbine Capacity: |
1.3 |
Height of Turbines: |
|
Calculated capacity: |
2.6 |
Site Address: |
The Hollies
High Lane
Croft
Skegness
pe24 4sh
|
|
|
County: |
Lincolnshire Region: East Midlands
|
OS Coordinates: |
549995 / 549995
|
Development Status: |
Operational
|
Application Submitted: |
7/2/2002
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
10/29/2004
|
Construction Date: |
9/1/2007
|
|
|
Generator Live |
1/1/2008
|
This Record Last Updated: |
1/6/2010
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
10/29/2004 |
Capacity: 5.2 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 25 m/s (55.925 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 4/3/2025 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017
Simon Mallett |
|