Kyle Wind Farm (Wind , Refused) Location in the UK : Scotland, East Ayrshire Type of installation: Wind on/offshore: on Turbines :50 Capacity : 255 MW Approx Date of 1st power generation: 2023
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
Key project facts
50 turbines (installed capacity up to 170MW)
149.5 metres to blade tip
30.6 km of new forest roads
26 km of upgraded forest roads
electricity substation compound
underground cables
permanent welfare facility for workers
Model: |
aa 3mw turbine
|
Start Speed: |
5
|
Capacity: |
3
|
Optimal Speed: |
15
|
Rotor Diameter: |
90
|
Stop Speed: |
25
|
Hub Height |
0 Avg for all turbines:
|
Avg. Elevation: |
|
Web Page: |
|
Comment: |
For proposed where turbine not yet agreed
|
Relationship |
Company (For:
Kyle
) |
Sorry I found no matches, Please try again.
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Kyle Windfarm 255 MW
|
Energy Type: |
Wind Onshore |
County: |
Strathclyde Country: Scotland LPA: Scottish Government (S36)
|
Site ID and Reference: |
3235 / N00299W
District:
|
Applicant: |
AMEC
Application :
IEC3/73
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
85 |
Turbine Capacity: |
3 |
Height of Turbines: |
|
Calculated capacity: |
255 |
Site Address: |
Kyle forest, B714 road between New Cumnock and Dalmellington
|
|
|
County: |
Strathclyde Region: Scotland
|
OS Coordinates: |
249500 / 249500
|
Development Status: |
Planning Permission Refused
|
Application Submitted: |
10/29/2004
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
10/24/2008
|
Construction Date: |
|
|
|
Generator Live |
|
This Record Last Updated: |
6/9/2010
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
10/24/2008 |
Project Info |
North KYLE Brockwell Energy submitted an application to Scottish Ministers in September 2019 for the development of a wind energy project within North KYLE Forest in East Ayrshire.
North KYLE Energy Project This Environmental Impact Assessment Report (EIAR) has been prepared on behalf of North KYLE Wind Farm Limited (NKWFL or ‘the Applicant’) to accompany an application for consent to construct and operate a 54-turbine wind farm
Go ahead for £800m of new power projects in Fife and Grangemouth PPP added that development funding was also being made available to continue planning for the “nationally significant” 270MW North KYLE wind power scheme.
Onshore back in business with 1.5GW win SSE Renewables netted a contract for 220MW of its Viking wind farm - half of the Shetland project's 443MW overall capacity - in the round's largest offer.
Brockwell Energy’s 212MW North KYLE project in East Ayrshire followed in a close second.
A 50-turbine wind farm in southern Scotland will be up and running by 2023 South KYLE Windfarm, near Dalmellington, is set to be the firm’s largest onshore wind farm in the United Kingdom.
|
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017
Simon Mallett |
|