Loading
Page views this IP this session = 1 of 10 unsubscribed pagesLlangwyryfon Wind Farm
Click here for Generation Forecast for wind farms based on Met office data
Llangwyryfon Wind Farm (Wind , Active) Location in the UK : Wales, Ceredigion Type of installation: Wind on/offshore: on Turbines :11 Capacity : 9.35 MW Approx Date of 1st power generation: February 2004
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
Wind Prospect was appointed by Cumbria Wind Farms to act as project managers, planning supervisors and site supervisors for a repowering project at Llangwyryfon, near Aberystwyth, Ceredigion.
Prior to the re-powering the site consisted of 20 WEG 300 kW machines, which have now been replaced by 11 Vestas V52-850kW turbines.
Model: |
Vestas V52-850
|
Start Speed: |
2.5
|
Capacity: |
0.85
|
Optimal Speed: |
6.5
|
Rotor Diameter: |
52
|
Stop Speed: |
12
|
Hub Height |
40 Avg for all turbines:40
|
Avg. Elevation: |
315
|
Web Page: |
http://www.nrg-http://www.nrg-systems.hu/dok/V52_UK.pdf |
Comment: |
|
Llangwyryfon Windfarm Pwlldraenllwyn Farm Llangwyryfon Aberystwyth SY23 4SR Wales
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Llangwyryfon 9.4 MW
|
Energy Type: |
Wind Onshore |
County: |
Dyfed Country: Wales LPA: Ceredigion County Council
|
Site ID and Reference: |
3229 / N00286W
District:
|
Applicant: |
Westbury Windfarms
Application :
A01/1330
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
11 |
Turbine Capacity: |
0.84999999999999998 |
Height of Turbines: |
|
Calculated capacity: |
9.35 |
Site Address: |
Llangwyryfon,
Southeast Aberystwyth
Ceredigion
|
|
|
County: |
Dyfed Region: Wales
|
OS Coordinates: |
261752 / 261752
|
Development Status: |
Operational
|
Application Submitted: |
12/1/2001
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
|
|
|
Generator Live |
2/1/2004
|
This Record Last Updated: |
3/3/2010
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Llangwyryfon Windfarm
|
Generator Type: |
On-shore wind (RO code = RQ)
|
Scheme : |
RO
|
Generator ID: |
R00013RQWA
|
Capacity: |
9350
|
Status: |
Live
|
Accreditation Date: |
12/1/2001
|
|
|
Commission Date: |
6/1/1993
|
|
|
Applicant: |
Llangwryfon Windfarm Ltd
|
Applicant Address: |
Cumbria Wind Farms Ltd
Bryn Isel
10A Short Bridge St Newtown, Powys
SY16 2LW
|
Address: |
Llangwyryfon Windfarm
Pwlldraenllwyn Farm
Llangwyryfon
Aberystwyth
SY23 4SR
Wales
|
Site Name: |
Llangwyryfon Windfarm
|
Generator Type: |
Wind
|
Scheme : |
REGO
|
Generator ID: |
G00527NWWA
|
Capacity: |
9350
|
Status: |
Live
|
Accreditation Date: |
12/1/2001
|
|
|
Commission Date: |
6/1/1993
|
|
|
Applicant: |
Llangwryfon Windfarm Ltd
|
Applicant Address: |
Cumbria Wind Farms Ltd
Bryn Isel
10A Short Bridge St Newtown, Powys
SY16 2LW
|
Address: |
Llangwyryfon Windfarm
Pwlldraenllwyn Farm
Llangwyryfon
Aberystwyth
SY23 4SR
Wales
|
|
Assumptions: Capacity: 9350kW 9.35 MW, Thus over the month Capacity * 720 hours per month = 6732 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/03/2018 | | | 1958 | 20.94% | Issued | 01/02/2018 | | | 2570 | 27.49% | Issued | 01/01/2018 | | | 3727 | 39.86% | Issued | 01/12/2017 | | | 2640 | 28.24% | Issued | 01/11/2017 | | | 1998 | 21.37% | Issued | 01/10/2017 | | | 2594 | 27.74% | Issued | 01/09/2017 | | | 1816 | 19.42% | Issued | 01/08/2017 | | | 1285 | 13.74% | Issued | 01/07/2017 | | | 1106 | 11.83% | Issued | 01/06/2017 | | | 1742 | 18.63% | Issued | 01/05/2017 | | | 1509 | 16.14% | Issued | 01/04/2017 | | | 1327 | 14.19% | Issued | 01/04/2017 | | | 1 | 0.01% | Issued | 01/03/2017 | | | 2832 | 30.29% | Redeemed | 01/02/2017 | | | 2921 | 31.24% | Redeemed | 01/01/2017 | | | 2432 | 26.01% | Redeemed | Dec-16 | 0 | 2138 | 2138 | 22.87% | Issued | Nov-16 | 0 | 1714 | 1714 | 18.33% | Issued | Oct-16 | 0 | 1439 | 1439 | 15.39% | Issued | Sep-16 | 0 | 1708 | 1708 | 18.27% | Issued | Aug-16 | 0 | 1720 | 1720 | 18.40% | Issued | Jul-16 | 0 | 1510 | 1510 | 16.15% | Issued | Jun-16 | 0 | 803 | 809 | 8.65% | Issued | Jun-16 | 0 | 803 | 809 | 8.65% | Issued | May-16 | 0 | 1339 | 1339 | 14.32% | Issued | Apr-16 | 0 | 2029 | 2029 | 21.70% | Issued | Mar-16 | 0 | 1868 | 1868 | 19.98% | Redeemed | Feb-16 | 0 | 2648 | 2648 | 28.32% | Redeemed | Jan-16 | 0 | 3188 | 3188 | 34.10% | Redeemed | Dec-15 | 0 | 4323 | 4323 | 46.24% | Redeemed | Nov-15 | 0 | 3569 | 3569 | 38.17% | Redeemed | Oct-15 | 0 | 1356 | 1356 | 14.50% | Redeemed | Sep-15 | 0 | 1373 | 1373 | 14.68% | Redeemed | Aug-15 | 0 | 1331 | 1331 | 14.24% | Redeemed | Jul-15 | 1796 | 1797 | 1797 | 19.22% | Redeemed | Jun-15 | 1439 | 1439 | 1439 | 15.39% | Redeemed | May-15 | 2551 | 2551 | 2551 | 27.28% | Redeemed | Apr-15 | 1685 | 1685 | 1685 | 18.02% | Redeemed | Mar-15 | 2736 | 2736 | 2736 | 29.26% | Redeemed | Feb-15 | 1855 | 1855 | 1855 | 19.84% | Redeemed | Jan-15 | 3607 | 3608 | 3608 | 38.59% | Redeemed | Dec-14 | 3502 | 3502 | 3502 | 37.45% | Redeemed | Nov-14 | 2071 | 2070 | 2070 | 22.14% | Redeemed | Oct-14 | 2689 | 2689 | 2689 | 28.76% | Redeemed | Sep-14 | 682 | 675 | 682 | 7.29% | Redeemed | Aug-14 | 2126 | 2125 | 2125 | 22.73% | Redeemed | Jul-14 | 888 | 882 | 888 | 9.50% | Redeemed | Jun-14 | 605 | 596 | 604 | 6.46% | Redeemed | May-14 | 1458 | 1458 | 1458 | 15.59% | Redeemed | Apr-14 | 1628 | 1628 | 1628 | 17.41% | Redeemed | Mar-14 | 2362 | 2363 | 2363 | 25.27% | Redeemed | Feb-14 | 3451 | 3450 | 3450 | 36.90% | Redeemed | Jan-14 | 2870 | 2871 | 2871 | 30.71% | Redeemed | Dec-13 | 2944 | 2944 | 2944 | 31.49% | Redeemed | Nov-13 | 1742 | 1741 | 1741 | 18.62% | Redeemed | Oct-13 | 2645 | 2646 | 1 | 0.01% | Redeemed | Sep-13 | 1729 | 1729 | 1 | 0.01% | Redeemed | Aug-13 | 1205 | 1205 | 1205 | 12.89% | Redeemed | Jul-13 | 839 | 830 | 839 | 8.97% | Redeemed | Jun-13 | 1718 | 1718 | 1718 | 18.37% | Redeemed | May-13 | 2226 | 2226 | 2226 | 23.81% | Redeemed | Apr-13 | 2689 | 2688 | 2688 | 28.75% | Redeemed | Mar-13 | 2681 | 2681 | 2681 | 28.67% | Redeemed | Feb-13 | 2266 | 2266 | 2266 | 24.24% | Redeemed | Jan-13 | 2909 | 2909 | 2909 | 31.11% | Redeemed | Dec-12 | 3121 | 3121 | 3121 | 33.38% | Redeemed | Nov-12 | 1751 | 1751 | 1751 | 18.73% | Redeemed | Oct-12 | 2001 | 2001 | 2001 | 21.40% | Redeemed | Sep-12 | 1912 | 1912 | 1912 | 20.45% | Redeemed | Aug-12 | 1804 | 1804 | 1804 | 19.29% | Redeemed | Jul-12 | 1265 | 1265 | 1265 | 13.53% | Redeemed | Jun-12 | 2117 | 2118 | 2118 | 22.65% | Redeemed | May-12 | 1514 | 1514 | 1514 | 16.19% | Redeemed | Apr-12 | 1999 | 1999 | 1999 | 21.38% | Redeemed | Mar-12 | 1511 | 1510 | 1510 | 16.15% | Redeemed | Feb-12 | 1851 | 1851 | 1851 | 19.80% | Redeemed | Jan-12 | 3358 | 3358 | 3358 | 35.91% | Redeemed | Dec-11 | 4298 | 4298 | 4298 | 45.97% | Redeemed | Nov-11 | 2659 | 2660 | 2660 | 28.45% | Redeemed | Oct-11 | 3146 | 3146 | 3146 | 33.65% | Redeemed | Sep-11 | 2803 | 2803 | 2803 | 29.98% | Redeemed | Aug-11 | 1247 | 1247 | 1247 | 13.34% | Redeemed | Jul-11 | 1080 | 1072 | 1080 | 11.55% | Redeemed | Jun-11 | 1509 | 1509 | 1509 | 16.14% | Redeemed | May-11 | 3068 | 3068 | 3068 | 32.81% | Redeemed | Apr-11 | 1354 | 1354 | 1354 | 14.48% | Redeemed | Mar-11 | 1209 | 1202 | 1209 | 12.93% | Redeemed | Feb-11 | 2524 | 2523 | 2523 | 26.98% | Redeemed | Jan-11 | 1818 | 1818 | 1818 | 19.44% | Redeemed | Dec-10 | 1218 | 1218 | 1218 | 13.03% | Redeemed | Nov-10 | 1815 | 1815 | 1815 | 19.41% | Redeemed | Oct-10 | 2307 | 2307 | 2307 | 24.67% | Redeemed |
|
Capacity: 35.7 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 12 m/s (26.844 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 4/8/2025 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017
Simon Mallett |
|