Lowca Wind Farm (Wind , Active) Location in the UK : England, Cumbria, Workington Type of installation: Wind on/offshore: on Turbines :7 Capacity : 4.62 MW Approx Date of 1st power generation: March 2000
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
At Lowca the turbines are sited along the 50m high cliff tops above the Irish Sea, ensuring maximum exposure to coastal winds.
The wind farm took six months to construct and began generating electricity in March 2000. The wind farm can generate enough energy to supply 2500 homes, whilst saving 5220 tonnes of carbon dioxide.
Model: |
Vestas V47/660
|
Start Speed: |
4
|
Capacity: |
0.5
|
Optimal Speed: |
13
|
Rotor Diameter: |
47
|
Stop Speed: |
25
|
Hub Height |
40 Avg for all turbines:40
|
Avg. Elevation: |
46
|
Web Page: |
http://www.iufmrese.cict.fr/concours/2002/CG_2002STI_lycee/Pour_en_savoir_plus/Vestas_V47.pdf |
Comment: |
|
Lowca Wind Farm (Adj) Park House Farm High Harrington Workington CA14 5RU England
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Lowca Wind Farm 4.7 MW
|
Energy Type: |
Wind Onshore |
County: |
Cumbria Country: England LPA: Copeland Borough Council
|
Site ID and Reference: |
3611 / 07126W3
District:
|
Applicant: |
Windprospect
Application :
4/98/0486
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
7 |
Turbine Capacity: |
0.67000000000000004 |
Height of Turbines: |
|
Calculated capacity: |
4.69 |
Site Address: |
Lowca
Near Workington
Cumbria
|
|
|
County: |
Cumbria Region: North West
|
OS Coordinates: |
298600 / 298600
|
Development Status: |
Operational
|
Application Submitted: |
6/26/1998
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
10/14/1998
|
Construction Date: |
|
|
|
Generator Live |
4/1/2000
|
This Record Last Updated: |
6/23/2009
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
10/14/1998 |
Site Name: |
LOWCA
|
Generator Type: |
On-shore wind (RO code = RQ)
|
Scheme : |
RO
|
Generator ID: |
R00008RQEN
|
Capacity: |
4560
|
Status: |
Live
|
Accreditation Date: |
6/26/1998
|
|
|
Commission Date: |
3/1/2000
|
|
|
Applicant: |
Cumbria Wind Limited
|
Applicant Address: |
First Floor
3800 Parkside
Birmingham Business Park
Birmingham
B37 7YG
England
|
Address: |
Lowca Wind Farm
(Adj) Park House Farm
High Harrington
Workington
CA14 5RU
England
|
Site Name: |
LOWCA
|
Generator Type: |
Wind
|
Scheme : |
REGO
|
Generator ID: |
G00206NWEN
|
Capacity: |
4560
|
Status: |
Live
|
Accreditation Date: |
6/26/1998
|
|
|
Commission Date: |
3/1/2000
|
|
|
Applicant: |
Cumbria Wind Limited
|
Applicant Address: |
First Floor
3800 Parkside
Birmingham Business Park
Birmingham
B37 7YG
England
|
Address: |
Lowca Wind Farm
(Adj) Park House Farm
High Harrington
Workington
CA14 5RU
England
|
|
Assumptions: Capacity: 4560kW 4.56 MW, Thus over the month Capacity * 720 hours per month = 3283.2 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/04/2018 | | | 972 | 21.32% | Issued | 01/03/2018 | | | 886 | 19.43% | Issued | 01/02/2018 | | | 813 | 17.83% | Issued | 01/01/2018 | | | 1288 | 28.25% | Issued | 01/12/2017 | | | 983 | 21.56% | Issued | 01/11/2017 | | | 1066 | 23.38% | Issued | 01/10/2017 | | | 1579 | 34.63% | Issued | 01/09/2017 | | | 1138 | 24.96% | Retired | 01/08/2017 | | | 1099 | 24.10% | Retired | 01/07/2017 | | | 886 | 19.43% | Retired | 01/06/2017 | | | 1238 | 27.15% | Issued | 01/05/2017 | | | 582 | 12.76% | Issued | 01/04/2017 | | | 589 | 12.92% | Issued | 01/03/2017 | | | 1162 | 25.48% | Redeemed | 01/02/2017 | | | 1116 | 24.47% | Redeemed | 01/01/2017 | | | 1167 | 25.59% | Redeemed | Dec-16 | 0 | 1532 | 1532 | 33.60% | Issued | Nov-16 | 0 | 1019 | 1019 | 22.35% | Issued | Oct-16 | 0 | 682 | 682 | 14.96% | Retired | Sep-16 | 0 | 1392 | 1392 | 30.53% | Retired | Aug-16 | 0 | 986 | 986 | 21.62% | Retired | Jul-16 | 0 | 822 | 822 | 18.03% | Retired | Jun-16 | 0 | 473 | 475 | 10.42% | Issued | May-16 | 0 | 1009 | 1009 | 22.13% | Issued | Apr-16 | 0 | 869 | 869 | 19.06% | Issued | Mar-16 | 0 | 840 | 840 | 18.42% | Retired | Feb-16 | 0 | 1263 | 1263 | 27.70% | Retired | Jan-16 | 0 | 1426 | 1426 | 31.27% | Retired | Dec-15 | 0 | 1579 | 1579 | 34.63% | Retired | Nov-15 | 0 | 1647 | 1647 | 36.12% | Retired | Oct-15 | 0 | 781 | 781 | 17.13% | Retired | Sep-15 | 0 | 602 | 602 | 13.20% | Retired | Aug-15 | 0 | 1016 | 1016 | 22.28% | Retired | Jul-15 | 977 | 976 | 976 | 21.40% | Redeemed | Jun-15 | 808 | 808 | 808 | 17.72% | Redeemed | May-15 | 1348 | 1348 | 1348 | 29.56% | Redeemed | Apr-15 | 621 | 618 | 621 | 13.62% | Redeemed | Mar-15 | 1089 | 1089 | 109 | 2.39% | Redeemed | Feb-15 | 1055 | 1055 | 1055 | 23.14% | Redeemed | Jan-15 | 1535 | 1534 | 1042 | 22.85% | Redeemed | Dec-14 | 1343 | 1343 | 868 | 19.04% | Redeemed | Nov-14 | 892 | 893 | 893 | 19.58% | Redeemed | Oct-14 | 1332 | 1331 | 1331 | 29.19% | Redeemed | Sep-14 | 371 | 368 | 371 | 8.14% | Redeemed | Aug-14 | 1193 | 1193 | 1193 | 26.16% | Redeemed | Jul-14 | 550 | 550 | 550 | 12.06% | Redeemed | Jun-14 | 308 | 305 | 308 | 6.75% | Redeemed | May-14 | 782 | 782 | 782 | 17.15% | Redeemed | Apr-14 | 835 | 835 | 835 | 18.31% | Redeemed | Mar-14 | 1188 | 1188 | 1188 | 26.05% | Redeemed | Feb-14 | 1362 | 1362 | 1362 | 29.87% | Redeemed | Jan-14 | 805 | 805 | 805 | 17.65% | Redeemed | Dec-13 | 1008 | 1008 | 1008 | 22.11% | Redeemed | Nov-13 | 936 | 936 | 936 | 20.53% | Redeemed | Oct-13 | 1357 | 1357 | 1357 | 29.76% | Redeemed | Sep-13 | 825 | 825 | 825 | 18.09% | Redeemed | Aug-13 | 132 | 132 | 132 | 2.89% | Redeemed | Jul-13 | 369 | 366 | 369 | 8.09% | Redeemed | Jun-13 | 582 | 582 | 582 | 12.76% | Redeemed | May-13 | 1220 | 1220 | 1220 | 26.75% | Redeemed | Apr-13 | 1095 | 1095 | 1095 | 24.01% | Redeemed | Mar-13 | 641 | 641 | 641 | 14.06% | Redeemed | Feb-13 | 633 | 633 | 633 | 13.88% | Redeemed | Jan-13 | 1223 | 1223 | 1223 | 26.82% | Redeemed | Dec-12 | 1422 | 1422 | 1422 | 31.18% | Redeemed | Nov-12 | 1435 | 1436 | 1436 | 31.49% | Redeemed | Oct-12 | 1022 | 1022 | 1022 | 22.41% | Redeemed | Sep-12 | 1495 | 1494 | 1494 | 32.76% | Redeemed | Aug-12 | 809 | 810 | 810 | 17.76% | Redeemed | Jul-12 | 799 | 799 | 799 | 17.52% | Redeemed | Jun-12 | 812 | 812 | 812 | 17.81% | Redeemed | May-12 | 731 | 731 | 731 | 16.03% | Redeemed | Apr-12 | 866 | 865 | 865 | 18.97% | Redeemed | Mar-12 | 727 | 723 | 727 | 15.94% | Redeemed | Feb-12 | 1170 | 1170 | 1170 | 25.66% | Redeemed | Jan-12 | 1499 | 1499 | 1499 | 32.87% | Redeemed | Dec-11 | 1656 | 1656 | 1656 | 36.32% | Redeemed | Nov-11 | 1320 | 1320 | 1320 | 28.95% | Redeemed | Oct-11 | 1586 | 1586 | 1586 | 34.78% | Redeemed | Sep-11 | 1480 | 1480 | 1480 | 32.46% | Redeemed | Aug-11 | 845 | 845 | 845 | 18.53% | Redeemed | Jul-11 | 540 | 537 | 541 | 11.86% | Redeemed | Jun-11 | 776 | 776 | 776 | 17.02% | Redeemed | May-11 | 1702 | 1702 | 1702 | 37.32% | Redeemed | Apr-11 | 958 | 959 | 959 | 21.03% | Redeemed | Mar-11 | 756 | 755 | 755 | 16.56% | Redeemed | Feb-11 | 1178 | 1178 | 1178 | 25.83% | Redeemed | Jan-11 | 878 | 878 | 878 | 19.25% | Redeemed | Dec-10 | 636 | 636 | 636 | 13.95% | Redeemed | Nov-10 | 953 | 953 | 953 | 20.90% | Redeemed | Oct-10 | 971 | 971 | 971 | 21.29% | Redeemed |
|
Capacity: 9.24 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 25 m/s (55.925 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 11/24/2024 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Case Study - Medium Wind n 2016, Green Cat Renewable Developments Limited (GCRD) purchased the Deuchries Wind Farm project after the previous owner decided the project was no longer viable Source: greencat, Date and Time of entry: Friday, November 22, 2024 00:00
Little Crow Solar Park Little Crow Solar Park is in Lincolnshire and is situated 2.5km northwest of the village of Broughton and directly to the east of the British steelworks at Scunthorpe. Source: inrg, Date and Time of entry: Friday, November 22, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Monday, September 9, 2024 00:00
How many more wind turbines will the UK build?. The government says it wants to generate enough wind energy to be able to power every home in the UK by 2030. Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
|
|
©2017
Simon Mallett |
|