Loading
Page views this IP this session = 1 of 10 unsubscribed pagesMonan Wind Farm
Click here for Generation Forecast for wind farms based on Met office data
Monan Wind Farm (Wind , Active) Location in the UK : Scotland, Western Isles Type of installation: Wind on/offshore: on Turbines :3 Capacity : 2.5 MW Approx Date of 1st power generation: March 2015
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
North Harris Community Trust / Monan Community Wind Farm
Model: |
Wind Turbine- Generic
|
Start Speed: |
5
|
Capacity: |
2
|
Optimal Speed: |
15
|
Rotor Diameter: |
100
|
Stop Speed: |
25
|
Hub Height |
0 Avg for all turbines:0
|
Avg. Elevation: |
0
|
Web Page: |
|
Comment: |
|
Ceann An Ora Quarry Ardhasaig Isle Of Harris HS3 3AJ
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Monan Hill Wind Turbines 1.5 MW
|
Energy Type: |
Wind Onshore |
County: |
Western Isles Country: Scotland LPA: Comhairle nan Eilean Siar Council
|
Site ID and Reference: |
4629 / B1514
District:
|
Applicant: |
North Harris Trust
Application :
06/00290/FUL
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
3 |
Turbine Capacity: |
0.5 |
Height of Turbines: |
|
Calculated capacity: |
1.5 |
Site Address: |
500m North Of Ceann An Ora Quarry Ardhasaig Isle Of Harris
|
|
HS3 3AJ
|
County: |
Western Isles Region: Scotland
|
OS Coordinates: |
114171 / 114171
|
Development Status: |
Operational
|
Application Submitted: |
5/24/2006
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
7/1/2014
|
|
|
Generator Live |
3/19/2015
|
This Record Last Updated: |
3/17/2015
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Monan, North Harris
|
Generator Type: |
Wind
|
Scheme : |
REGO
|
Generator ID: |
G02221NWSC
|
Capacity: |
1470
|
Status: |
Live
|
Accreditation Date: |
5/24/2006
|
|
|
Commission Date: |
12/18/2014
|
|
|
Applicant: |
Windflow Hammer Limited
|
Applicant Address: |
9 Sutton Close
Cookham
Maidenhead
SL6 9QU
England
|
Address: |
500 m north of Ceann An Ora Quarry
Ardhasaig
North Harris
HS3 3AP
Scotland
|
|
Assumptions: Capacity: 1470kW 1.47 MW, Thus over the month Capacity * 720 hours per month = 1058.4 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/01/2017 | | | 220 | 14.97% | Redeemed | 01/12/2016 - 31/12/2016 | 0 | 0 | 335 | 22.79% | Issued | 01/11/2016 - 30/11/2016 | 0 | 0 | 231 | 15.71% | Issued | 01/10/2016 - 31/10/2016 | 0 | 0 | 200 | 13.61% | Issued | 01/09/2016 - 30/09/2016 | 0 | 0 | 268 | 18.23% | Issued | 01/08/2016 - 31/08/2016 | 0 | 0 | 218 | 14.83% | Issued | 01/07/2016 - 31/07/2016 | 0 | 0 | 175 | 11.90% | Issued | Jun-16 | 0 | 0 | 132 | 8.98% | Issued | May-16 | 0 | 0 | 145 | 9.86% | Issued | Apr-16 | 0 | 0 | 200 | 13.61% | Issued | Mar-16 | 0 | 0 | 146 | 9.93% | Redeemed | Feb-16 | 0 | 0 | 155 | 10.54% | Redeemed | Jan-16 | 0 | 0 | 372 | 25.31% | Redeemed | Dec-15 | 0 | 0 | 476 | 32.38% | Redeemed | Nov-15 | 0 | 0 | 336 | 22.86% | Redeemed | Oct-15 | 0 | 0 | 204 | 13.88% | Redeemed | Sep-15 | 0 | 0 | 161 | 10.95% | Redeemed | Aug-15 | 0 | 0 | 212 | 14.42% | Redeemed | Jul-15 | 172 | 0 | 175 | 11.90% | Redeemed | Jun-15 | 185 | 0 | 186 | 12.65% | Redeemed | May-15 | 352 | 0 | 357 | 24.29% | Redeemed | Apr-15 | 123 | 0 | 124 | 8.44% | Redeemed | Mar-15 | 109 | 0 | 110 | 7.48% | Expired | Feb-15 | 49 | 0 | 50 | 3.40% | Expired | | | | 304 | 20.68% | Issued | | | | 172 | 11.70% | Issued | | | | 133 | 9.05% | Issued | | | | 217 | 14.76% | Issued | | | | 321 | 21.84% | Issued | | | | 198 | 13.47% | Issued | | | | 187 | 12.72% | Issued | | | | 263 | 17.89% | Issued | | | | 326 | 22.18% | Issued | | | | 341 | 23.20% | Issued |
|
Capacity: 5 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 25 m/s (55.925 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 1/18/2025 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017