Hook Moor Wind Farm (Wind , Active) Location in the UK : England, Garforth Type of installation: Wind on/offshore: on Turbines :5 Capacity : 15 MW Approx Date of 1st power generation: January 2016
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
Planning permission granted at public inquiry on 11 October 2011, decision issued 9 December 2011.
Model: |
Senvion MM92
|
Start Speed: |
4
|
Capacity: |
2
|
Optimal Speed: |
12
|
Rotor Diameter: |
92
|
Stop Speed: |
25
|
Hub Height |
80 Avg for all turbines:80
|
Avg. Elevation: |
64
|
Web Page: |
http://www.repower.de/wind-power-solutions/wind-turbines/5m/ |
Comment: |
The reliable gearbox and generator technology of the MM82 is also the basis for the MM92 wind power plants.
|
Hook Moor Wind Farm Collier Lane Aberford Leeds LS25 3EB England
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Hook Moor 10.3 MW
|
Energy Type: |
Wind Onshore |
County: |
West Yorkshire Country: England LPA: Leeds City Council
|
Site ID and Reference: |
4658 / EN00422
District:
|
Applicant: |
Banks Renewables
Application :
08/01118/FU
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
3 |
Turbine Capacity: |
2.0499999999999998 |
Height of Turbines: |
125 |
Calculated capacity: |
6.15 |
Site Address: |
Land at Hook Moor
, Micklefield
, Leeds
|
|
|
County: |
West Yorkshire Region: Yorkshire and Humber
|
OS Coordinates: |
443851 / 443851
|
Development Status: |
Operational
|
Application Submitted: |
2/26/2008
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
8/4/2009
|
Construction Date: |
3/11/2015
|
|
|
Generator Live |
1/15/2016
|
This Record Last Updated: |
2/26/2016
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
8/4/2009 |
Site Name: |
Hook Moor Wind Farm
|
Generator Type: |
On-shore wind (RO code = RQ)
|
Scheme : |
RO
|
Generator ID: |
R00363RQEN
|
Capacity: |
9871
|
Status: |
Live
|
Accreditation Date: |
2/26/2008
|
|
|
Commission Date: |
11/18/2015
|
|
|
Applicant: |
Banks Renewables (Hook Moor Wind Farm) Ltd
|
Applicant Address: |
Inkerman House
St Johns Road
Meadowfield
DURHAM
DH7 8XL
England
|
Address: |
Hook Moor Wind Farm
Collier Lane
Aberford
Leeds
LS25 3EB
England
|
Site Name: |
Hook Moor Wind Farm
|
Generator Type: |
Wind
|
Scheme : |
REGO
|
Generator ID: |
G02885NWEN
|
Capacity: |
9871
|
Status: |
Live
|
Accreditation Date: |
2/26/2008
|
|
|
Commission Date: |
11/18/2015
|
|
|
Applicant: |
Banks Renewables (Hook Moor Wind Farm) Ltd
|
Applicant Address: |
Inkerman House
St Johns Road
Meadowfield
DURHAM
DH7 8XL
England
|
Address: |
Hook Moor Wind Farm
Collier Lane
Aberford
Leeds
LS25 3EB
England
|
|
Assumptions: Capacity: 9871kW 9.871 MW, Thus over the month Capacity * 720 hours per month = 7107.12 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/04/2018 | | | 2314 | 23.44% | Issued | 01/03/2018 | | | 2815 | 28.52% | Issued | 01/02/2018 | | | 2207 | 22.36% | Issued | 01/01/2018 | | | 3342 | 33.86% | Issued | 01/12/2017 | | | 3434 | 34.79% | Issued | 01/11/2017 | | | 2723 | 27.59% | Issued | 01/11/2017 | | | 107 | 1.08% | Issued | 01/10/2017 | | | 3297 | 33.40% | Issued | 01/09/2017 | | | 1868 | 18.92% | Issued | 01/08/2017 | | | 1983 | 20.09% | Issued | 01/07/2017 | | | 1768 | 17.91% | Issued | 01/06/2017 | | | 2488 | 25.21% | Issued | 01/05/2017 | | | 1963 | 19.89% | Issued | 01/04/2017 | | | 1990 | 20.16% | Issued | 01/03/2017 | | | 2539 | 25.72% | Redeemed | 01/02/2017 | | | 2544 | 25.77% | Redeemed | 01/01/2017 | | | 2072 | 20.99% | Redeemed | Dec-16 | 0 | 1796 | 1995 | 20.21% | Issued | Nov-16 | 0 | 2037 | 2264 | 22.94% | Issued | Oct-16 | 0 | 1493 | 1659 | 16.81% | Issued | Sep-16 | 0 | 1353 | 1504 | 15.24% | Issued | Aug-16 | 0 | 628 | 1260 | 12.76% | Revoked | Jul-16 | 0 | 1621 | 1801 | 18.25% | Issued | Jul-16 | 0 | 1621 | 1801 | 18.25% | Issued | Jun-16 | 0 | 1072 | 1192 | 12.08% | Issued | May-16 | 0 | 1827 | 2031 | 20.58% | Issued | Apr-16 | 0 | 1833 | 2037 | 20.64% | Issued | Mar-16 | 0 | 1766 | 1962 | 19.88% | Issued | Feb-16 | 0 | 2435 | 2705 | 27.40% | Issued | Jan-16 | 0 | 2811 | 3124 | 31.65% | Issued | Dec-15 | 0 | 3544 | 107 | 1.08% | Revoked | Nov-15 | 0 | 407 | 456 | 4.62% | Pending Tr |
|
Capacity: 30 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 25 m/s (55.925 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 12/27/2024 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Case Study - Medium Wind n 2016, Green Cat Renewable Developments Limited (GCRD) purchased the Deuchries Wind Farm project after the previous owner decided the project was no longer viable Source: greencat, Date and Time of entry: Friday, November 22, 2024 00:00
Little Crow Solar Park Little Crow Solar Park is in Lincolnshire and is situated 2.5km northwest of the village of Broughton and directly to the east of the British steelworks at Scunthorpe. Source: inrg, Date and Time of entry: Friday, November 22, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Monday, September 9, 2024 00:00
How many more wind turbines will the UK build?. The government says it wants to generate enough wind energy to be able to power every home in the UK by 2030. Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
|
|
©2017
Simon Mallett |
|