Page views this IP this session = 1 of 10 unsubscribed pagesGlen App Wind Farm
Click here for Generation Forecast for wind farms based on Met office data
Glen App Wind Farm (Wind , Agreed/Planning) Location in the UK : Scotland, ballantrae Type of installation: Wind on/offshore: on Turbines :14 Capacity : 32 MW Approx Date of 1st power generation: January 2017
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
Planning application submitted to South Ayrshire Council in September 2012
September 2016: Glen App is now under construction
Model: |
Gamesa G90
|
Start Speed: |
6
|
Capacity: |
2
|
Optimal Speed: |
10
|
Rotor Diameter: |
90
|
Stop Speed: |
23
|
Hub Height |
80 Avg for all turbines:80
|
Avg. Elevation: |
214
|
Web Page: |
http://tinyurl.com/gamesag80 |
Comment: |
|
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Glen App 22 MW
|
Energy Type: |
Wind Onshore |
County: |
Strathclyde Country: Scotland LPA: South Ayrshire Council
|
Site ID and Reference: |
4593 / AA305
District:
|
Applicant: |
Scottish Power Renewables
Application :
12/01156/APPM
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
11 |
Turbine Capacity: |
2 |
Height of Turbines: |
|
Calculated capacity: |
22 |
Site Address: |
NE/o Cairnryan, Stranraer, Dumfries and Galloway
|
|
|
County: |
Strathclyde Region: Scotland
|
OS Coordinates: |
208880 / 208880
|
Development Status: |
Operational
|
Application Submitted: |
10/2/2012
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
10/13/2016
|
|
|
Generator Live |
1/15/2017
|
This Record Last Updated: |
7/19/2017
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Glen App
|
Generator Type: |
On-shore wind (ROS code = SQ)
|
Scheme : |
RO
|
Generator ID: |
R00318SQSC
|
Capacity: |
22000
|
Status: |
Live
|
Accreditation Date: |
10/2/2012
|
|
|
Commission Date: |
1/6/2017
|
|
|
Applicant: |
ScottishPower Renewables (UK) Limited
|
Applicant Address: |
Arnott House
12-16 Bridge Street
Belfast
BT1 1LB
Northern Ireland
|
Address: |
Glen App Windfarm
Glen App Estate
off A77
Nr. Cairnryan
KA26 0PG
Scotland
|
Site Name: |
Glen App
|
Generator Type: |
Wind
|
Scheme : |
REGO
|
Generator ID: |
G02543NWSC
|
Capacity: |
22000
|
Status: |
Live
|
Accreditation Date: |
10/2/2012
|
|
|
Commission Date: |
1/6/2017
|
|
|
Applicant: |
ScottishPower Renewables (UK) Limited
|
Applicant Address: |
Arnott House
12-16 Bridge Street
Belfast
BT1 1LB
Northern Ireland
|
Address: |
Glen App Windfarm
Glen App Estate
off A77
Nr. Cairnryan
KA26 0PG
Scotland
|
|
Assumptions: Capacity: 22000kW 22 MW, Thus over the month Capacity * 720 hours per month = 15840 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/03/2018 | | | 4555 | 20.70% | Issued | 01/02/2018 | | | 5595 | 25.43% | Issued | 01/01/2018 | | | 7688 | 34.95% | Issued | 01/12/2017 | | | 6160 | 28.00% | Issued | 01/11/2017 | | | 5571 | 25.32% | Issued | 01/10/2017 | | | 5955 | 27.07% | Issued | 01/09/2017 | | | 5017 | 22.80% | Issued | 01/08/2017 | | | 3440 | 15.64% | Issued | 01/07/2017 | | | 3216 | 14.62% | Issued | 01/06/2017 | | | 3389 | 15.40% | Issued |
|
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|