Loading
Page views this IP this session = 7 of 10 unsubscribed pagesReaps Moss Wind Farm
Click here for Generation Forecast for wind farms based on Met office data
Reaps Moss Wind Farm (Wind , Active) Location in the UK : England, bacup Type of installation: Wind on/offshore: on Turbines :3 Capacity : 9 MW Approx Date of 1st power generation: March 2015
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
Coronation Power wishes to develop a small 3 turbine wind farm on land known as Reaps Moss, an area of moorland east of Bacup, east Lancashire.
Coronation Power has secured planning permission for a small 3 turbine wind farm on land known as Reaps Moss, an area of moorland east of Bacup, east Lancashire. The scheme was approved in October 2009 and subject to final agreement from DEFRA with regard to common land issues, construction is expected to start in 2012
Model: |
Senvion M104
|
Start Speed: |
4
|
Capacity: |
3.4
|
Optimal Speed: |
11
|
Rotor Diameter: |
104
|
Stop Speed: |
25
|
Hub Height |
73 Avg for all turbines:73
|
Avg. Elevation: |
416
|
Web Page: |
http://www.repower.de/fileadmin/download/produkte/RE_PP_3.4M104_uk.pdf |
Comment: |
|
Reaps Moss Wind FarmLand off Todmorden Road Bacup Rossendale OL13 9XF England
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Reaps Moss Wind Farm 10.2 MW
|
Energy Type: |
Wind Onshore |
County: |
Lancashire Country: England LPA: Rossendale Borough Council
|
Site ID and Reference: |
4655 / EN00261
District:
|
Applicant: |
Infrared Capital Partners
Application :
2007/125
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
3 |
Turbine Capacity: |
3.3999999999999999 |
Height of Turbines: |
125 |
Calculated capacity: |
10.2 |
Site Address: |
Reaps Moss, Bacup
|
|
|
County: |
Lancashire Region: North West
|
OS Coordinates: |
389065 / 389065
|
Development Status: |
Operational
|
Application Submitted: |
2/19/2007
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
10/1/2014
|
|
|
Generator Live |
3/31/2015
|
This Record Last Updated: |
2/24/2016
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Reaps Moss Wind Farm 9 MW
|
Energy Type: |
Wind Onshore |
County: |
Lancashire Country: England LPA: Rossendale Borough Council
|
Site ID and Reference: |
2609 / 07037W5
District:
|
Applicant: |
S B ENERGY LTD
Application :
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
9 |
Turbine Capacity: |
1 |
Height of Turbines: |
|
Calculated capacity: |
9 |
Site Address: |
Off A681, Bacup,
|
|
|
County: |
Lancashire Region: North West
|
OS Coordinates: |
389000 / 389000
|
Development Status: |
Revised
|
Application Submitted: |
6/1/1999
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
2/21/2000
|
Construction Date: |
|
|
|
Generator Live |
|
This Record Last Updated: |
10/8/2013
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
2/21/2000 |
Site Name: |
Reaps Moss
|
Generator Type: |
On-shore wind (RO code = RQ)
|
Scheme : |
RO
|
Generator ID: |
R00354RQEN
|
Capacity: |
10140
|
Status: |
Live
|
Accreditation Date: |
6/1/1999
|
|
|
Commission Date: |
9/2/2015
|
|
|
Applicant: |
Reaps Moss Limited
|
Applicant Address: |
InfraRed Capital Partners
12 Charles II Street
London
SW1Y 4QU
England
|
Address: |
Reaps Moss Wind Farm
Land off Todmorden Road
Bacup
Rossendale
OL13 9XF
England
|
Site Name: |
Reaps Moss
|
Generator Type: |
Wind
|
Scheme : |
REGO
|
Generator ID: |
G02797NWEN
|
Capacity: |
10140
|
Status: |
Live
|
Accreditation Date: |
6/1/1999
|
|
|
Commission Date: |
9/2/2015
|
|
|
Applicant: |
Reaps Moss Limited
|
Applicant Address: |
InfraRed Capital Partners
12 Charles II Street
London
SW1Y 4QU
England
|
Address: |
Reaps Moss Wind Farm
Land off Todmorden Road
Bacup
Rossendale
OL13 9XF
England
|
|
Assumptions: Capacity: 10140kW 10.14 MW, Thus over the month Capacity * 720 hours per month = 7300.8 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/04/2018 | | | 3107 | 30.64% | Issued | 01/03/2018 | | | 2535 | 25.00% | Issued | 01/02/2018 | | | 3301 | 32.55% | Issued | 01/01/2018 | | | 4442 | 43.81% | Issued | 01/12/2017 | | | 3650 | 36.00% | Issued | 01/11/2017 | | | 3841 | 37.88% | Issued | 01/10/2017 | | | 4325 | 42.65% | Issued | 01/09/2017 | | | 2605 | 25.69% | Issued | 01/08/2017 | | | 2628 | 25.92% | Issued | 01/07/2017 | | | 2639 | 26.03% | Issued | 01/06/2017 | | | 3128 | 30.85% | Issued | 01/05/2017 | | | 2862 | 28.22% | Issued | 01/04/2017 | | | 2980 | 29.39% | Issued | 01/03/2017 | | | 4008 | 39.53% | Issued | 01/02/2017 | | | 3668 | 36.17% | Issued | 01/01/2017 | | | 2733 | 26.95% | Issued | Dec-16 | 0 | 3362 | 3735 | 36.83% | Issued | Nov-16 | 0 | 2719 | 3021 | 29.79% | Issued | Oct-16 | 0 | 2466 | 2740 | 27.02% | Issued | Sep-16 | 0 | 2544 | 2032 | 20.04% | Issued | Aug-16 | 0 | 2667 | 2963 | 29.22% | Issued | Jul-16 | 0 | 2379 | 2643 | 26.07% | Issued | Jul-16 | 0 | 2379 | 2643 | 26.07% | Issued | Jun-16 | 0 | 1063 | 1181 | 11.65% | Issued | May-16 | 0 | 2402 | 2669 | 26.32% | Issued | Apr-16 | 0 | 2431 | 2701 | 26.64% | Issued | Mar-16 | 0 | 2381 | 2646 | 26.09% | Redeemed | Feb-16 | 0 | 3222 | 3580 | 35.31% | Redeemed | Jan-16 | 0 | 3468 | 3853 | 38.00% | Redeemed | Dec-15 | 0 | 4833 | 5370 | 52.96% | Redeemed | Nov-15 | 0 | 3692 | 4102 | 40.45% | Redeemed | Oct-15 | 0 | 2136 | 2373 | 23.40% | Redeemed | Sep-15 | 0 | 1548 | 1720 | 16.96% | Redeemed |
|
Capacity: 20.4 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 25 m/s (55.925 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 4/3/2025 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017
Simon Mallett |
|