Moray East Wind Farm (Wind , Agreed/Planning) Location in the UK : Scotland, moray firth Type of installation: Wind on/offshore: off Turbines :100 Capacity : 950 MW Approx Date of 1st power generation: 2022
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
Moray Offshore Renewables Granted Consent For 1116 MW Offshore Wind Development In The Outer Moray Firth Moray East and Moray West
Model: |
Vestas V164-9.5MW
|
Start Speed: |
0
|
Capacity: |
9.5
|
Optimal Speed: |
0
|
Rotor Diameter: |
164
|
Stop Speed: |
0
|
Hub Height |
105 Avg for all turbines:
|
Avg. Elevation: |
|
Web Page: |
https://en.wind-turbine-models.com/turbines/1605-mhi-vestas-offshore-v164-9.5-mw |
Comment: |
|
Relationship |
Company (For:
Moray East
) |
Sorry I found no matches, Please try again.
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Moray West Offshore Wind Farm Project 882 MW
|
Energy Type: |
Wind Offshore |
County: |
Offshore Country: Scotland LPA: Marine Scotland
|
Site ID and Reference: |
6158 /
District:
|
Applicant: |
EDPR
Application :
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
60 |
Turbine Capacity: |
14.699999999999999 |
Height of Turbines: |
230 |
Calculated capacity: |
882 |
Site Address: |
Smith Bank, Moray Firth - 22.5 km off Lybster
|
|
KW2
|
County: |
Offshore Region: Offshore
|
OS Coordinates: |
322637 / 322637
|
Development Status: |
Under Construction
|
Application Submitted: |
7/5/2018
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
5/1/2022
|
|
|
Generator Live |
|
This Record Last Updated: |
10/27/2022
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
6/13/2044 |
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Moray East 950 MW
|
Energy Type: |
Wind Offshore |
County: |
Offshore Country: Scotland LPA: Scottish Government (S36)
|
Site ID and Reference: |
2534 / A0246
District:
|
Applicant: |
Diamond Green Limited, CTG & Ocean Winds
Application :
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
100 |
Turbine Capacity: |
9.5 |
Height of Turbines: |
204 |
Calculated capacity: |
950 |
Site Address: |
Smith Bank, Moray Firth - 13miles off Lybster
|
|
|
County: |
Offshore Region: Offshore
|
OS Coordinates: |
353328 / 353328
|
Development Status: |
Operational
|
Application Submitted: |
8/28/2012
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
6/6/2019
|
|
|
Generator Live |
4/1/2022
|
This Record Last Updated: |
4/12/2023
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
MW
|
Energy Type: |
|
County: |
Country: LPA:
|
Site ID and Reference: |
/
District:
|
Applicant: |
Application :
|
(Go to search to find Application) |
Site Address: |
|
|
|
County: |
Region:
|
OS Coordinates: |
/
|
Development Status: |
|
Application Submitted: |
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
|
|
|
Generator Live |
|
This Record Last Updated: |
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
MW
|
Energy Type: |
|
County: |
Country: LPA:
|
Site ID and Reference: |
/
District:
|
Applicant: |
Application :
|
(Go to search to find Application) |
Site Address: |
|
|
|
County: |
Region:
|
OS Coordinates: |
/
|
Development Status: |
|
Application Submitted: |
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
|
|
|
Generator Live |
|
This Record Last Updated: |
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
|
Generator Type: |
|
Scheme : |
|
Generator ID: |
|
Capacity: |
|
Status: |
|
Accreditation Date: |
|
|
|
Commission Date: |
|
|
|
Applicant: |
|
Applicant Address: |
|
Address: |
|
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Case Study - Medium Wind n 2016, Green Cat Renewable Developments Limited (GCRD) purchased the Deuchries Wind Farm project after the previous owner decided the project was no longer viable Source: greencat, Date and Time of entry: Friday, November 22, 2024 00:00
Little Crow Solar Park Little Crow Solar Park is in Lincolnshire and is situated 2.5km northwest of the village of Broughton and directly to the east of the British steelworks at Scunthorpe. Source: inrg, Date and Time of entry: Friday, November 22, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Monday, September 9, 2024 00:00
How many more wind turbines will the UK build?. The government says it wants to generate enough wind energy to be able to power every home in the UK by 2030. Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
|
|
©2017
Simon Mallett |
|