Page views this IP this session = 1 of 10 unsubscribed pagesEveley Solar Farm
Eveley Solar Farm (Solar , Active) Location in the UK : England, SO20 6SA Type of installation: Solar on/offshore: on Solar Panels :189000 Capacity : 49 MW Acreage:150 or approx Hectares : 60 Approx Date of 1st power generation: march 2015
/YES
When complete, the 150-acre project at Eveley Farm, near Houghton, Hampshire, will cover the equivalent of 85 football pitches with 189,000 reflective solar panels.
Eveley Farm Stevens Drove Houghton Stockbridge SO20 6SA
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Eveley Farm 49 MW
|
Energy Type: |
Solar Photovoltaics |
County: |
Hampshire Country: England LPA: Test Valley Borough Council
|
Site ID and Reference: |
5080 /
District:
|
Applicant: |
PS Renewables
Application :
15/00094/FULLS
|
(Go to search to find Application) |
|
--- For Solar Farms / Parks --- |
Mounting of panels: |
Ground |
|
|
|
--- ----- ---- --- |
Site Address: |
Land At Eveley Farm Stevens Drove Houghton Stockbridge
|
|
SO20 6SA
|
County: |
Hampshire Region: South East
|
OS Coordinates: |
432987 / 432987
|
Development Status: |
Operational
|
Application Submitted: |
2/16/2015
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
3/1/2016
|
|
|
Generator Live |
3/17/2016
|
This Record Last Updated: |
3/23/2016
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
7/27/2018 |
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Eveley Farm 49 MW
|
Energy Type: |
Solar Photovoltaics |
County: |
Hampshire Country: England LPA: Test Valley Borough Council
|
Site ID and Reference: |
1873 / IF1299
District:
|
Applicant: |
Kronos Solar
Application :
13/02735/FULLS
|
(Go to search to find Application) |
|
--- For Solar Farms / Parks --- |
Mounting of panels: |
Ground |
|
|
|
--- ----- ---- --- |
Site Address: |
Stevens Drove, Houghton, Stockbridge,
|
|
SO20 6SA
|
County: |
Hampshire Region: South East
|
OS Coordinates: |
432987 / 432987
|
Development Status: |
Revised
|
Application Submitted: |
12/11/2013
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
8/15/2014
|
Construction Date: |
|
|
|
Generator Live |
|
This Record Last Updated: |
9/30/2015
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
11/26/2014 |
Called In: |
|
Appeal Withdrawn: |
7/1/2015 |
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
8/15/2014 |
Site Name: |
Eveley Solar PV Farm
|
Generator Type: |
Photovoltaic (RO code = RU)
|
Scheme : |
RO
|
Generator ID: |
R00690RUEN
|
Capacity: |
41800
|
Status: |
Live
|
Accreditation Date: |
12/11/2013
|
|
|
Commission Date: |
3/17/2016
|
|
|
Applicant: |
Primrose Solar (16) Limited
|
Applicant Address: |
3rd floor
Connaught House
1-3 Mount Street
London
W1K 3NB
England
|
Address: |
Land at Eveley Farm
Stevens Drove
Houghton
SO20 6SA
England
|
Site Name: |
Eveley Solar PV Farm
|
Generator Type: |
Photovoltaic
|
Scheme : |
REGO
|
Generator ID: |
G07248PVEN
|
Capacity: |
41800
|
Status: |
Live
|
Accreditation Date: |
12/11/2013
|
|
|
Commission Date: |
3/17/2016
|
|
|
Applicant: |
Primrose Solar (16) Limited
|
Applicant Address: |
3rd floor
Connaught House
1-3 Mount Street
London
W1K 3NB
England
|
Address: |
Land at Eveley Farm
Stevens Drove
Houghton
SO20 6SA
England
|
|
Assumptions: Capacity: 41800kW 41.8 MW, Thus over the month Capacity * 720 hours per month = 30096 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/04/2018 | | | 4457 | 10.66% | Issued | 01/03/2018 | | | 3154 | 7.55% | Issued | 01/02/2018 | | | 3070 | 7.34% | Issued | 01/01/2018 | | | 1306 | 3.12% | Issued | 01/12/2017 | | | 1031 | 2.47% | Issued | 01/11/2017 | | | 1773 | 4.24% | Issued | 01/10/2017 | | | 2864 | 6.85% | Issued | 01/09/2017 | | | 4144 | 9.91% | Issued | 01/08/2017 | | | 5733 | 13.72% | Issued | 01/07/2017 | | | 6417 | 15.35% | Issued | 01/06/2017 | | | 6964 | 16.66% | Issued | 01/05/2017 | | | 6657 | 15.93% | Issued | 01/04/2017 | | | 6532 | 15.63% | Issued | 01/03/2017 | | | 4041 | 9.67% | Redeemed | 01/02/2017 | | | 1748 | 4.18% | Redeemed | 01/01/2017 | | | 1364 | 3.26% | Redeemed | Dec-16 | 0 | 1262 | 1038 | 2.48% | Issued | Nov-16 | 0 | 2157 | 1710 | 4.09% | Issued | Oct-16 | 0 | 4622 | 3602 | 8.62% | Issued | Sep-16 | 0 | 5119 | 3974 | 9.51% | Issued | Aug-16 | 0 | 8730 | 6716 | 16.07% | Issued | Jul-16 | 0 | 7691 | 5916 | 14.15% | Issued | Jun-16 | 0 | 7158 | 5507 | 13.17% | Issued | May-16 | 0 | 9443 | 7264 | 17.38% | Issued | Apr-16 | 0 | 7323 | 5676 | 13.58% | Issued | Mar-16 | 0 | 2454 | 1915 | 4.58% | Redeemed |
|
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017
Simon Mallett |
|