Site Name: |
Woodhouse Fields Farm 5 MW
|
Energy Type: |
Solar Photovoltaics |
County: |
Staffordshire Country: England LPA: East Staffordshire Borough Council
|
Site ID and Reference: |
5577 /
District:
|
Applicant: |
Wirsol
Application :
P/2015/01032
|
(Go to search to find Application) |
|
--- For Solar Farms / Parks --- |
Mounting of panels: |
Ground |
|
|
|
--- ----- ---- --- |
Site Address: |
Land To East Of, Nab Lane, Rocester, Uttoxeter
|
|
ST14 5JB
|
County: |
Staffordshire Region: West Midlands
|
OS Coordinates: |
408847 / 408847
|
Development Status: |
Operational
|
Application Submitted: |
8/7/2015
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
12/10/2016
|
|
|
Generator Live |
2/10/2017
|
This Record Last Updated: |
7/19/2018
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
11/20/2020 |
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Woodhouse
|
Generator Type: |
Photovoltaic (RO code = RU)
|
Scheme : |
RO
|
Generator ID: |
R00920RUEN
|
Capacity: |
3990
|
Status: |
Live
|
Accreditation Date: |
8/7/2015
|
|
|
Commission Date: |
2/10/2017
|
|
|
Applicant: |
Woodhouse Solar Limited
|
Applicant Address: |
Wirsol Solar Energy Ltd
Unit 5e
Arundel
BN18 0AG
England
|
Address: |
Woodhouse Solar Park
Woodhouse Fields Farm
Rocester
ST14 5HY
England
|
Site Name: |
Woodhouse
|
Generator Type: |
Photovoltaic
|
Scheme : |
REGO
|
Generator ID: |
G07840PVEN
|
Capacity: |
3990
|
Status: |
Live
|
Accreditation Date: |
8/7/2015
|
|
|
Commission Date: |
2/10/2017
|
|
|
Applicant: |
Woodhouse Solar Limited
|
Applicant Address: |
Wirsol Solar Energy Ltd
Unit 5e
Arundel
BN18 0AG
England
|
Address: |
Woodhouse Solar Park
Woodhouse Fields Farm
Rocester
ST14 5HY
England
|
|
Assumptions: Capacity: 3990kW 3.99 MW, Thus over the month Capacity * 720 hours per month = 2872.8 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/04/2018 | | | 436 | 10.93% | Issued | 01/03/2018 | | | 326 | 8.17% | Issued | 01/02/2018 | | | 234 | 5.86% | Issued | 01/01/2018 | | | 115 | 2.88% | Issued | 01/12/2017 | | | 77 | 1.93% | Issued | 01/11/2017 | | | 165 | 4.14% | Issued | 01/10/2017 | | | 223 | 5.59% | Retired | 01/09/2017 | | | 394 | 9.87% | Retired | 01/08/2017 | | | 585 | 14.66% | Retired | 01/07/2017 | | | 643 | 16.12% | Retired | 01/06/2017 | | | 584 | 14.64% | Retired | 01/05/2017 | | | 667 | 16.72% | Issued | 01/04/2017 | | | 568 | 14.24% | Issued | 01/03/2017 | | | 380 | 9.52% | Redeemed | 01/02/2017 | | | 60 | 1.50% | Redeemed |
|
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017