Page views this IP this session = 1 of 10 unsubscribed pagesWharrels Hill Wind Farm
Click here for Generation Forecast for wind farms based on Met office data
Wharrels Hill Wind Farm (Wind , Active) Location in the UK : England, Cumbria Type of installation: Wind on/offshore: on Turbines :8 Capacity : 10.4 MW Approx Date of 1st power generation: August 2007
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
The Wharrels Hill Wind Farm project includes the involvement of six local farmers to build and operate a substantial wind farm in Cumbria. Operating since 2007 it was one of FIM’s first projects.
Prior to construction, the consented site was purchased from Npower Renewables by Wharrels Hill LLP, a group of private investors. Oxfordshire based FIM Services manages Wharrels Hill LLP and Wind Prospect Ltd conductucted the project management during the construction phase.
Model: |
Nordex N60/1300
|
Start Speed: |
4.5
|
Capacity: |
1.3
|
Optimal Speed: |
10
|
Rotor Diameter: |
60
|
Stop Speed: |
25
|
Hub Height |
70 Avg for all turbines:70
|
Avg. Elevation: |
211
|
Web Page: |
http://www.nordex-online.com/fileadmin/MEDIA/Produktinfos/EN/Nordex_N60_EN.pdf |
Comment: |
|
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Wharrels Hill Wind Farm 10.4 MW
|
Energy Type: |
Wind Onshore |
County: |
Cumbria Country: England LPA: Allerdale Borough Council
|
Site ID and Reference: |
2618 / 07060W4
District:
|
Applicant: |
Wharrels Hill Windfarm Ltd/ National Windpower
Application :
2/2001/0008
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
8 |
Turbine Capacity: |
1.3 |
Height of Turbines: |
|
Calculated capacity: |
10.4 |
Site Address: |
Wharrels Hill
Bothel
Cumbria
|
|
|
County: |
Cumbria Region: North West
|
OS Coordinates: |
318000 / 318000
|
Development Status: |
Operational
|
Application Submitted: |
12/23/2000
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
6/19/2002
|
Construction Date: |
4/1/2007
|
|
|
Generator Live |
8/7/2007
|
This Record Last Updated: |
5/6/2009
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
6/19/2002 |
Site Name: |
WHARRELS HILL WINDFARM
|
Generator Type: |
Wind
|
Scheme : |
REGO
|
Generator ID: |
G00951NWEN
|
Capacity: |
10297
|
Status: |
Live
|
Accreditation Date: |
12/23/2000
|
|
|
Commission Date: |
3/1/2007
|
|
|
Applicant: |
FIM Services Limited
|
Applicant Address: |
Glebe Barn
Great Barrington
Burford Oxon
OX18 4US
|
Address: |
Wharrells Hill Windfarm LLP
Wharrells Hill Windfarm LLPWharrells HillB
Bothel
CA7 2JL
England
|
|
Assumptions: Capacity: 10297kW 10.297 MW, Thus over the month Capacity * 720 hours per month = 7413.84 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/04/2018 | | | 1994 | 19.36% | Issued | 01/03/2018 | | | 2313 | 22.46% | Issued | 01/02/2018 | | | 1411 | 13.70% | Issued | 01/01/2018 | | | 2819 | 27.38% | Issued | 01/12/2017 | | | 2063 | 20.03% | Issued | 01/11/2017 | | | 1581 | 15.35% | Issued | 01/10/2017 | | | 3019 | 29.32% | Issued | 01/09/2017 | | | 1317 | 12.79% | Issued | 01/08/2017 | | | 1516 | 14.72% | Issued | 01/07/2017 | | | 1013 | 9.84% | Issued | 01/06/2017 | | | 1938 | 18.82% | Issued | 01/05/2017 | | | 1563 | 15.18% | Issued | 01/04/2017 | | | 1381 | 13.41% | Issued | 01/03/2017 | | | 2246 | 21.81% | Redeemed | 01/02/2017 | | | 2421 | 23.51% | Redeemed | 01/01/2017 | | | 1793 | 17.41% | Redeemed | Dec-16 | 0 | 2727 | 2727 | 26.48% | Issued | Nov-16 | 0 | 1043 | 1043 | 10.13% | Issued | Oct-16 | 0 | 967 | 967 | 9.39% | Issued | Sep-16 | 0 | 1876 | 1876 | 18.22% | Issued | Aug-16 | 0 | 1724 | 1724 | 16.74% | Issued | Jul-16 | 0 | 1477 | 1477 | 14.34% | Issued | Jul-16 | 0 | 1477 | 1477 | 14.34% | Issued | Jun-16 | 0 | 762 | 770 | 7.48% | Issued | Jun-16 | 0 | 762 | 770 | 7.48% | Issued | May-16 | 0 | 1822 | 1822 | 17.69% | Issued | Apr-16 | 0 | 1397 | 1397 | 13.57% | Issued | Mar-16 | 0 | 1429 | 1429 | 13.88% | Redeemed | Feb-16 | 0 | 2497 | 2497 | 24.25% | Redeemed | Jan-16 | 0 | 2607 | 2607 | 25.32% | Redeemed | Dec-15 | 0 | 3878 | 3878 | 37.66% | Redeemed | Nov-15 | 0 | 3267 | 2851 | 27.69% | Redeemed | Oct-15 | 0 | 913 | 155 | 1.51% | Issued | Sep-15 | 0 | 633 | 642 | 6.23% | Redeemed | Aug-15 | 0 | 1539 | 1539 | 14.95% | Redeemed | Jul-15 | 1565 | 1565 | 1565 | 15.20% | Redeemed | Jun-15 | 1578 | 1577 | 1577 | 15.32% | Redeemed | May-15 | 2497 | 2497 | 2497 | 24.25% | Redeemed | Apr-15 | 1513 | 1504 | 1513 | 14.69% | Redeemed | Mar-15 | 2897 | 2897 | 2897 | 28.13% | Redeemed | Feb-15 | 1854 | 1858 | 4 | 0.04% | Redeemed | Jan-15 | 3556 | 3561 | 5 | 0.05% | Redeemed | Dec-14 | 3068 | 3073 | 3068 | 29.80% | Redeemed | Nov-14 | 1199 | 1204 | 1199 | 11.64% | Redeemed | Oct-14 | 2861 | 2863 | 2 | 0.02% | Redeemed | Sep-14 | 511 | 511 | 7 | 0.07% | Redeemed | Aug-14 | 1762 | 1766 | 4 | 0.04% | Redeemed | Jul-14 | 958 | 958 | 958 | 9.30% | Redeemed | Jun-14 | 471 | 472 | 8 | 0.08% | Redeemed | May-14 | 1466 | 1469 | 21 | 0.20% | Redeemed | Apr-14 | 1509 | 1514 | 5 | 0.05% | Redeemed | Mar-14 | 2701 | 2703 | 2703 | 26.25% | Redeemed | Feb-14 | 3673 | 3675 | 3675 | 35.69% | Expired | Jan-14 | 2774 | 2775 | 2775 | 26.95% | Expired | Dec-13 | 3531 | 3532 | 3532 | 34.30% | Expired | Nov-13 | 1550 | 1554 | 1554 | 15.09% | Expired | Oct-13 | 2434 | 2434 | 1 | 0.01% | Redeemed | Sep-13 | 1379 | 1379 | 1378 | 13.38% | Redeemed | Aug-13 | 1342 | 1342 | 1342 | 13.03% | Redeemed | Jul-13 | 736 | 728 | 736 | 7.15% | Redeemed | Jun-13 | 1063 | 1057 | 1063 | 10.32% | Redeemed | May-13 | 1917 | 1917 | 1917 | 18.62% | Redeemed | Apr-13 | 2507 | 2507 | 2507 | 24.35% | Redeemed | Mar-13 | 1919 | 1919 | 1919 | 18.64% | Redeemed | Feb-13 | 1413 | 1413 | 1413 | 13.72% | Redeemed | Jan-13 | 2563 | 2563 | 2563 | 24.89% | Redeemed | Dec-12 | 2349 | 2348 | 2348 | 22.80% | Redeemed | Nov-12 | 2103 | 2103 | 2103 | 20.42% | Redeemed | Oct-12 | 1221 | 1222 | 1222 | 11.87% | Redeemed | Sep-12 | 2245 | 2245 | 2245 | 21.80% | Redeemed | Aug-12 | 1170 | 1170 | 1170 | 11.36% | Redeemed | Jul-12 | 1264 | 1263 | 1263 | 12.27% | Redeemed | Jun-12 | 1422 | 1422 | 1422 | 13.81% | Redeemed | May-12 | 1331 | 1331 | 1331 | 12.93% | Redeemed | Apr-12 | 1626 | 1626 | 1626 | 15.79% | Redeemed | Mar-12 | 1405 | 1405 | 1405 | 13.64% | Redeemed | Feb-12 | 2090 | 2090 | 2090 | 20.30% | Redeemed | Jan-12 | 2994 | 2994 | 2994 | 29.08% | Redeemed | Dec-11 | 3640 | 3641 | 3641 | 35.36% | Redeemed | Nov-11 | 2674 | 2674 | 2674 | 25.97% | Redeemed | Oct-11 | 2861 | 2861 | 2861 | 27.78% | Redeemed | Sep-11 | 2634 | 2634 | 2634 | 25.58% | Redeemed | Aug-11 | 1022 | 1022 | 1022 | 9.93% | Redeemed | Jul-11 | 599 | 592 | 599 | 5.82% | Redeemed | Jun-11 | 1156 | 1156 | 1156 | 11.23% | Redeemed | May-11 | 2854 | 2854 | 2854 | 27.72% | Redeemed | Apr-11 | 1783 | 1783 | 1783 | 17.32% | Redeemed | Mar-11 | 1250 | 1243 | 1250 | 12.14% | Redeemed | Feb-11 | 1933 | 1933 | 1933 | 18.77% | Redeemed | Jan-11 | 1529 | 1529 | 1529 | 14.85% | Redeemed | Dec-10 | 605 | 599 | 606 | 5.89% | Redeemed | Nov-10 | 1857 | 1857 | 1857 | 18.03% | Redeemed | Oct-10 | 1654 | 1654 | 1654 | 16.06% | Redeemed |
|
Capacity: 20.8 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 25 m/s (55.925 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 11/23/2024 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Case Study - Medium Wind n 2016, Green Cat Renewable Developments Limited (GCRD) purchased the Deuchries Wind Farm project after the previous owner decided the project was no longer viable Source: greencat, Date and Time of entry: Friday, November 22, 2024 00:00
Little Crow Solar Park Little Crow Solar Park is in Lincolnshire and is situated 2.5km northwest of the village of Broughton and directly to the east of the British steelworks at Scunthorpe. Source: inrg, Date and Time of entry: Friday, November 22, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Monday, September 9, 2024 00:00
How many more wind turbines will the UK build?. The government says it wants to generate enough wind energy to be able to power every home in the UK by 2030. Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
|
|
©2017
Simon Mallett |
|