Loading
Page views this IP this session = 1 of 10 unsubscribed pagesAfton Wind Farm
Click here for Generation Forecast for wind farms based on Met office data
Afton Wind Farm (Wind , Active) Location in the UK : Scotland, new cumnock Type of installation: Wind on/offshore: on Turbines :25 Capacity : 74 MW Approx Date of 1st power generation: February 2018
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
Proposals involve developing a site on land which forms part of the Afton Reservoir catchment area, approximately 8km south of New Cumnock, East Ayrshire.
Model: |
Gamesa G80
|
Start Speed: |
6
|
Capacity: |
2
|
Optimal Speed: |
13
|
Rotor Diameter: |
80
|
Stop Speed: |
21
|
Hub Height |
70 Avg for all turbines:70
|
Avg. Elevation: |
526
|
Web Page: |
http://www.gamesacorp.com/recursos/doc/productos-servicios/aerogeneradores/catalogo-g9x-20-mw-eng.pdf |
Comment: |
|
New Cumnock adjacent to Afton reservoir
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Afton Wind Farm 50 MW
|
Energy Type: |
Wind Onshore |
County: |
Strathclyde Country: Scotland LPA: Scottish Government (S36)
|
Site ID and Reference: |
4262 / N00302W
District:
|
Applicant: |
InfraRed Capital Partners/ E.on
Application :
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
25 |
Turbine Capacity: |
2 |
Height of Turbines: |
120 |
Calculated capacity: |
50 |
Site Address: |
To the south west of New Cumnock adjacent to Afton reservoir
|
|
|
County: |
Strathclyde Region: Scotland
|
OS Coordinates: |
262100 / 262100
|
Development Status: |
Operational
|
Application Submitted: |
11/3/2004
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
8/16/2016
|
|
|
Generator Live |
2/15/2018
|
This Record Last Updated: |
10/2/2018
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Capacity: 100 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 21 m/s (46.977 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 6/1/2025 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
Red Rock Power AFTON AFTON Wind Farm is an operational 50 MW onshore wind development in East Ayrshire, Scotland. The wind farm will power up to 35,000 homes each year and is expected to generate 3.5 million MWh of electricity in its lifetime.
Red Rock on the money at AFTON Red Rock Power has secured £80m (€91m) from NatWest bank for the 50MW AFTON wind farm in East Ayrshire, Scotland.
InfraRed buys AFTON Wind Farm from E.ON AFTON Wind Farm, which was developed by E.ON Climate & Renewables, will be a 25 turbine, 50MW onshore wind farm located on land adjacent to AFTON Reservoir near New Cumnock.
Wind farm worker dies after being stranded by heavy snow The 74-year-old security guard and a 42-year-old colleague were working on Sunday at AFTON Wind Farm, which is under construction near New Cumnock in East Ayrshire
ShAFTON The ShAFTON turbine is located on the former ShAFTON Two-Gates Coking site which lies between the villages of Grimethorpe and Cudworth.
|
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017
Simon Mallett |
|