Lochaber (Hydro , Active) Location in the UK : Scotland, Highland Type of installation: Hydro on/offshore: on Turbines :0 Capacity : 84 MW Approx Date of 1st power generation: 1929
/YES
Constructed in three phases between 1924 and 1944, the scheme was the work of engineers Charles Meik and William Halcrow for the British Aluminium Company
Scottish and Southern Energy Renewables is proposing a 600Mw pumped storage scheme which would extract, store and release energy, to the north-west of Lochy Lochy in the Great Glen
Relationship |
Company (For:
Lochaber
) |
Sorry I found no matches, Please try again.
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Lochaber 65 MW
|
Energy Type: |
Large Hydro |
County: |
Highland Country: Scotland LPA: Scottish Government (S36)
|
Site ID and Reference: |
6601 /
District:
|
Applicant: |
GFG Alliance
Application :
|
(Go to search to find Application) |
Site Address: |
Fort William
|
|
|
County: |
Highland Region: Scotland
|
OS Coordinates: |
212621 / 212621
|
Development Status: |
Operational
|
Application Submitted: |
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
1/1/1924
|
|
|
Generator Live |
1/1/1929
|
This Record Last Updated: |
4/5/2018
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017
Simon Mallett |
|