Loading
Page views this IP this session = 1 of 10 unsubscribed pagesStoke
Stoke ( , Active) Location in the UK : England, ST4 4DX Type of installation: on/offshore: on Turbines :0 Capacity : 14.2 MW Approx Date of 1st power generation: January 1998
/YES
MES Environmental (CNIM Group) Operational Stoke Incinerator Campbell Road Stoke-on-Trent ST4 4DX England
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Stoke-on-Trent EfW 14.2 MW
|
Energy Type: |
EfW Incineration |
County: |
Staffordshire Country: England LPA: Stoke on Trent City Council
|
Site ID and Reference: |
815 / 05034M3
District:
|
Applicant: |
MES Environmental (CNIM Group)
Application :
|
(Go to search to find Application) |
Site Address: |
Stoke-on-Trent Waste Incinerator Plant,
Campbell Road,
Sideway, Stoke on Trent
Staffordshire
|
|
|
County: |
Staffordshire Region: West Midlands
|
OS Coordinates: |
387800 / 387800
|
Development Status: |
Operational
|
Application Submitted: |
12/6/1994
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
|
|
|
Generator Live |
1/10/1998
|
This Record Last Updated: |
4/30/2010
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
STOKE INCINERATOR
|
Generator Type: |
Biodegradable (REGO code = MW)
|
Scheme : |
REGO
|
Generator ID: |
G00008MWEN
|
Capacity: |
13000
|
Status: |
Live
|
Accreditation Date: |
12/6/1994
|
|
|
Commission Date: |
1/1/1998
|
|
|
Applicant: |
Stoke Incinerator
|
Applicant Address: |
Mese Suite
Fountain House Great Cornbow
Halesowen West Midlands
B63 3BL
|
Address: |
Stoke Incinerator
Campbell Road
Stoke-on-Trent
ST4 4DX
England
|
|
Assumptions: Capacity: 13000kW 13 MW, Thus over the month Capacity * 720 hours per month = 9360 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
| | | 3668 | 28.22% | Issued | | | | 4079 | 31.38% | Issued | | | | 4018 | 30.91% | Redeemed | | | | 3841 | 29.55% | Redeemed | 01/01/2017 | | | 4322 | 33.25% | Redeemed | 01/12/2016 - 31/12/2016 | 0 | 0 | 211 | 1.62% | Issued | 01/11/2016 - 30/11/2016 | 0 | 0 | 4265 | 32.81% | Issued | 01/10/2016 - 31/10/2016 | 0 | 0 | 4242 | 32.63% | Issued | 01/09/2016 - 30/09/2016 | 0 | 0 | 3260 | 25.08% | Issued | 01/08/2016 - 31/08/2016 | 0 | 0 | 142 | 1.09% | Issued | 01/07/2016 - 31/07/2016 | 0 | 0 | 1267 | 9.75% | Issued | Jun-16 | 0 | 0 | 3670 | 28.23% | Issued | Jun-16 | 0 | 0 | 3670 | 28.23% | Issued | May-16 | 0 | 0 | 4357 | 33.52% | Issued | Apr-16 | 0 | 0 | 4339 | 33.38% | Issued | Mar-16 | 0 | 0 | 4018 | 30.91% | Redeemed | Feb-16 | 0 | 0 | 3276 | 25.20% | Redeemed | Jan-16 | 0 | 0 | 3730 | 28.69% | Redeemed | Dec-15 | 0 | 0 | 4409 | 33.92% | Redeemed | Nov-15 | 0 | 0 | 3415 | 26.27% | Redeemed | Oct-15 | 0 | 0 | 4229 | 32.53% | Redeemed | Sep-15 | 0 | 0 | 3959 | 30.45% | Redeemed | Aug-15 | 0 | 0 | 1321 | 10.16% | Redeemed | Jul-15 | 4212 | 0 | 4212 | 32.40% | Redeemed | Jun-15 | 4277 | 0 | 4277 | 32.90% | Redeemed | May-15 | 3920 | 0 | 3921 | 30.16% | Redeemed | Apr-15 | 4749 | 0 | 4749 | 36.53% | Redeemed | Mar-15 | 3926 | 0 | 3926 | 30.20% | Redeemed | Feb-15 | 4264 | 0 | 4263 | 32.79% | Redeemed | Jan-15 | 4558 | 0 | 4558 | 35.06% | Redeemed | Dec-14 | 4623 | 0 | 4623 | 35.56% | Redeemed | Nov-14 | 4200 | 0 | 4199 | 32.30% | Redeemed | Oct-14 | 2419 | 0 | 2420 | 18.62% | Redeemed | Jul-14 | 2842 | 0 | 2842 | 21.86% | Redeemed | Jun-14 | 4160 | 0 | 4160 | 32.00% | Redeemed | May-14 | 3994 | 0 | 3994 | 30.72% | Redeemed | Apr-14 | 4235 | 0 | 4235 | 32.58% | Redeemed | Mar-14 | 3795 | 0 | 3795 | 29.19% | Redeemed | Feb-14 | 3186 | 0 | 3186 | 24.51% | Redeemed | Jan-14 | 2948 | 0 | 2948 | 22.68% | Redeemed | Dec-13 | 3243 | 0 | 3243 | 24.95% | Redeemed | Nov-13 | 3404 | 0 | 1 | 0.01% | Expired | Oct-13 | 4240 | 0 | 4239 | 32.61% | Redeemed | Sep-13 | 3880 | 0 | 3880 | 29.85% | Redeemed | Aug-13 | 1267 | 0 | 1267 | 9.75% | Redeemed | Jul-13 | 3210 | 0 | 3210 | 24.69% | Redeemed | Jun-13 | 3075 | 0 | 3075 | 23.65% | Redeemed | May-13 | 3193 | 0 | 2604 | 20.03% | Expired | Apr-13 | 3428 | 0 | 3428 | 26.37% | Redeemed | Mar-13 | 3807 | 0 | 3807 | 29.28% | Expired | Feb-13 | 2987 | 0 | 2987 | 22.98% | Expired | Jan-13 | 2605 | 0 | 2604 | 20.03% | Redeemed | Dec-12 | 3948 | 0 | 1210 | 9.31% | Expired | Nov-12 | 3801 | 0 | 2340 | 18.00% | Expired | Oct-12 | 4114 | 0 | 1170 | 9.00% | Expired | Sep-12 | 3900 | 0 | 3900 | 30.00% | Redeemed | Aug-12 | 1840 | 0 | 1840 | 14.15% | Redeemed | Jul-12 | 3212 | 0 | 3212 | 24.71% | Redeemed | Jun-12 | 3766 | 0 | 3765 | 28.96% | Redeemed | May-12 | 4516 | 0 | 4516 | 34.74% | Redeemed | Apr-12 | 4326 | 0 | 4326 | 33.28% | Redeemed | Mar-12 | 4234 | 0 | 4233 | 32.56% | Redeemed | Feb-12 | 3972 | 0 | 3972 | 30.55% | Redeemed | Jan-12 | 4515 | 0 | 4515 | 34.73% | Redeemed | Dec-11 | 4592 | 0 | 4592 | 35.32% | Redeemed | Nov-11 | 4137 | 0 | 4136 | 31.82% | Redeemed | Oct-11 | 4549 | 0 | 4549 | 34.99% | Redeemed | Sep-11 | 2004 | 0 | 2005 | 15.42% | Redeemed | Aug-11 | 2805 | 0 | 2805 | 21.58% | Redeemed | Jul-11 | 3281 | 0 | 3281 | 25.24% | Redeemed | Jun-11 | 3061 | 0 | 3062 | 23.55% | Redeemed | May-11 | 3777 | 0 | 3777 | 29.05% | Redeemed | Apr-11 | 4003 | 0 | 4003 | 30.79% | Redeemed | Mar-11 | 3932 | 0 | 3932 | 30.25% | Redeemed | Feb-11 | 4026 | 0 | 4026 | 30.97% | Redeemed | Jan-11 | 4165 | 0 | 4165 | 32.04% | Redeemed | Dec-10 | 3992 | 0 | 3992 | 30.71% | Redeemed | Nov-10 | 3887 | 0 | 3888 | 29.91% | Redeemed | Oct-10 | 3991 | 0 | 3991 | 30.70% | Redeemed | | | | 3131 | 24.08% | Issued | | | | 3016 | 23.20% | Issued | | | | 3949 | 30.38% | Issued | | | | 3302 | 25.40% | Retired | | | | 3820 | 29.38% | Issued | | | | 3937 | 30.28% | Issued | | | | 3925 | 30.19% | Issued | | | | 3976 | 30.58% | Issued | | | | 584 | 4.49% | Issued | | | | 3602 | 27.71% | Issued |
|
Project Info |
Shell to become single off-taker of largest solar farm in England Shell Energy Europe has signed an initial five year power purchase agreement (PPA) with British Solar Renewables (BSR) to take power generated at England’s largest solar farm at RAF Lyneham. The 69.8MW BradenSTOKE solar power plant,
Shell signs PPA with England’s largest solar farm Shell has signed a deal to buy all of the power from England’s largest solar park, the 69.8MW BradenSTOKE development, once RAF Lyneham, near Swindon.
Triodos banks on UK solar with £18 million double refinancing package The two sites in question are the 15.1MW STOKEs Marsh solar farm in Coulston, Wiltshire, and the 5MW Stoneshill solar farm in Exeter.
Jobs Cars Property Directory Announcements Sign In Search MORE NEWS TRANSPORT CR The plans for the 78 metre high turbine – the height of a 25 storey building – on Maple Hill off Chilton Street, Clare, was opposed by Clare, STOKE by Clare, Hundon, Ashen and Kedington parish councils
Solar farm to power 4,000 homes after scaled-back plans approved Purbeck District Council (PDC) planning board members agreed proposals for the 12 MW plant, set for land at STOKEford Farm, East STOKE, after visiting the site.
|
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017
Simon Mallett |
|