Loading
Page views this IP this session = 1 of 10 unsubscribed pagesHazelside Wind Farm
Click here for Generation Forecast for wind farms based on Met office data
Hazelside Wind Farm (Wind , Proposed) Location in the UK : Scotland, ML11 0SD Type of installation: Wind on/offshore: on Turbines :2 Capacity : 1.6 MW Approx Date of 1st power generation:
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
Model: |
|
Start Speed: |
|
Capacity: |
|
Optimal Speed: |
|
Rotor Diameter: |
|
Stop Speed: |
|
Hub Height |
Avg for all turbines:
|
Avg. Elevation: |
|
Web Page: |
|
Comment: |
|
side Farm, Lanark, Strathclyde
Relationship |
Company (For:
Hazelside
) |
Sorry I found no matches, Please try again.
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Hazelside farm 1.6 MW
|
Energy Type: |
Wind Onshore |
County: |
Strathclyde Country: Scotland LPA: South Lanarkshire Council
|
Site ID and Reference: |
3633 / C2874
District:
|
Applicant: |
Mitchell Farming Partnerships (3R Energy)
Application :
CL/14/0132
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
2 |
Turbine Capacity: |
0.80000000000000004 |
Height of Turbines: |
|
Calculated capacity: |
1.6 |
Site Address: |
side Farm, Lanark,
|
|
ML11 0SD
|
County: |
Strathclyde Region: Scotland
|
OS Coordinates: |
281251 / 281251
|
Development Status: |
Under Construction
|
Application Submitted: |
4/1/2014
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
2/15/2016
|
|
|
Generator Live |
|
This Record Last Updated: |
1/16/2020
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
12/18/2017 |
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Hazelside farm 2.4 MW
|
Energy Type: |
Wind Onshore |
County: |
Strathclyde Country: Scotland LPA: South Lanarkshire Council
|
Site ID and Reference: |
3445 / IF1128
District:
|
Applicant: |
Mitchell Farming Partnerships (3R Energy)
Application :
CL/12/0493
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
3 |
Turbine Capacity: |
0.80000000000000004 |
Height of Turbines: |
|
Calculated capacity: |
2.4 |
Site Address: |
Glespin, Lanark,
|
|
|
County: |
Strathclyde Region: Scotland
|
OS Coordinates: |
281162 / 281162
|
Development Status: |
Revised
|
Application Submitted: |
11/15/2012
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
|
|
|
Generator Live |
|
This Record Last Updated: |
1/19/2014
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
5/31/2013 |
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Hazelside Farm 500
|
Generator Type: |
Wind
|
Scheme : |
REGO
|
Generator ID: |
G02504NWSC
|
Capacity: |
500
|
Status: |
Live
|
Accreditation Date: |
11/15/2012
|
|
|
Commission Date: |
9/16/2016
|
|
|
Applicant: |
William Mitchell
|
Applicant Address: |
Newtonhead Farm
Ayr Road
LANARK
ML11 9TU
Scotland
|
Address: |
Hazelside Farm
Douglas
Lanark
ML11 0SD
Scotland
|
|
Assumptions: Capacity: 500kW 0.5 MW, Thus over the month Capacity * 720 hours per month = 360 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
| | | 168 | 33.60% | Issued | | | | 117 | 23.40% | Issued | | | | 128 | 25.60% | Redeemed | | | | 109 | 21.80% | Redeemed | 01/01/2017 | | | 93 | 18.60% | Redeemed | 01/12/2016 - 31/12/2016 | 0 | 0 | 69 | 13.80% | Issued | 01/11/2016 - 30/11/2016 | 0 | 0 | 59 | 11.80% | Issued | 01/10/2016 - 31/10/2016 | 0 | 0 | 54 | 10.80% | Issued | Oct-16 | 0 | 0 | 54 | 10.80% | Issued | Sep-16 | 0 | 0 | 48 | 9.60% | Issued | 01/09/2016 - 30/09/2016 | 0 | 0 | 48 | 9.60% | Issued | | | | 154 | 30.80% | Issued | | | | 64 | 12.80% | Issued | | | | 177 | 35.40% | Issued | | | | 104 | 20.80% | Issued | | | | 108 | 21.60% | Issued | | | | 74 | 14.80% | Issued | | | | 162 | 32.40% | Issued | | | | 211 | 42.20% | Issued | | | | 103 | 20.60% | Issued | | | | 158 | 31.60% | Issued | | | | 130 | 26.00% | Issued |
|
Project Info |
Sorry I found no matches, Please try again.
|
|
©2018
Simon Mallett |
Latest News Added |
Case Study - Medium Wind n 2016, Green Cat Renewable Developments Limited (GCRD) purchased the Deuchries Wind Farm project after the previous owner decided the project was no longer viable Source: greencat, Date and Time of entry: Friday, November 22, 2024 00:00
Little Crow Solar Park Little Crow Solar Park is in Lincolnshire and is situated 2.5km northwest of the village of Broughton and directly to the east of the British steelworks at Scunthorpe. Source: inrg, Date and Time of entry: Friday, November 22, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Monday, September 9, 2024 00:00
How many more wind turbines will the UK build?. The government says it wants to generate enough wind energy to be able to power every home in the UK by 2030. Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
|
|
©2017
Simon Mallett |
|