Dummuie Wind Farm (Wind , Active) Location in the UK : Scotland, Aberdeenshire Type of installation: Wind on/offshore: on Turbines :7 Capacity : 10.4 MW Approx Date of 1st power generation: April 2007
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
The Dummuie Wind Farm, developed and built by Eco2, started operating in April 2007. Located in Huntly, Aberdeenshire, it is now owned by IKEA Energy Services Ltd with Eco2 providing operational services.
Model: |
Vestas V66
|
Start Speed: |
5
|
Capacity: |
2
|
Optimal Speed: |
15
|
Rotor Diameter: |
66
|
Stop Speed: |
25
|
Hub Height |
47 Avg for all turbines:47
|
Avg. Elevation: |
265
|
Web Page: |
|
Comment: |
|
East Mains Dummuie Drumblade Huntly Aberdeensh AB54 4RL Scotland
Relationship |
Company (For:
Dummuie
) |
Sorry I found no matches, Please try again.
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Dummuie 12.3 MW
|
Energy Type: |
Wind Onshore |
County: |
Grampian Country: Scotland LPA: Aberdeenshire Council
|
Site ID and Reference: |
3200 / N00211W
District:
|
Applicant: |
Tetro Energy Ltd (ECO2)
Application :
APP/2003/0084
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
7 |
Turbine Capacity: |
1.75 |
Height of Turbines: |
|
Calculated capacity: |
12.25 |
Site Address: |
East Dummuie
Huntly
|
|
|
County: |
Grampian Region: Scotland
|
OS Coordinates: |
358600 / 358600
|
Development Status: |
Operational
|
Application Submitted: |
8/20/2003
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
2/20/2004
|
Construction Date: |
6/1/2006
|
|
|
Generator Live |
1/1/2007
|
This Record Last Updated: |
6/4/2015
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
2/20/2004 |
Site Name: |
Dummuies Windfarm - A
|
Generator Type: |
On-shore wind (ROS code = SQ)
|
Scheme : |
RO
|
Generator ID: |
R00075SQSC
|
Capacity: |
12250
|
Status: |
Live
|
Accreditation Date: |
8/20/2003
|
|
|
Commission Date: |
1/1/2007
|
|
|
Applicant: |
Dummuies Windfarm Huntly Limited
|
Applicant Address: |
Vision House, Oak Tree Court
Mulberry Drive
Cardiff Gate Business Park
Cardiff
CF23 8RS
Wales
|
Address: |
Dummuies Windfarm - A (01.02.07)
East MainsDummuieDrumbladeHuntlyAberdeensh
AB54 4RL
Scotland
|
Capacity: 24.5 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 25 m/s (55.925 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 1/28/2025 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|