Loading
Page views this IP this session = 1 of 10 unsubscribed pagesWangford Energy from Waste Plant
Wangford (Waste , Active, Waste - Landfill Gas) Location in the UK : England, Eastern England Type of installation: Waste on/offshore: on Turbines :0 Capacity : 0.87 MW Approx Date of 1st power generation:
/YES
Wanford, Beccles, Suffolk, NR34 8AR
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
WANGFORD LANDFILL SITE
|
Generator Type: |
Landfill Gas (REGO code = LG)
|
Scheme : |
REGO
|
Generator ID: |
G00240LGEN
|
Capacity: |
975
|
Status: |
Live
|
Accreditation Date: |
|
|
|
Commission Date: |
12/1/1999
|
|
|
Applicant: |
Novera Energy Generation No2 Ltd
|
Applicant Address: |
1030 Centre Park
Slutchers Lane
Warrington
WA1 1QL
England
|
Address: |
Wangford Landfill Site
Wangford
Beccles
NR34 8AU
England
|
|
Assumptions: Capacity: 975kW 0.975 MW, Thus over the month Capacity * 720 hours per month = 702 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/03/2018 | | | 233 | 23.90% | Issued | 01/02/2018 | | | 271 | 27.79% | Issued | 01/01/2018 | | | 325 | 33.33% | Issued | 01/12/2017 | | | 409 | 41.95% | Issued | 01/11/2017 | | | 349 | 35.79% | Issued | 01/10/2017 | | | 397 | 40.72% | Issued | 01/09/2017 | | | 414 | 42.46% | Issued | 01/08/2017 | | | 296 | 30.36% | Issued | 01/07/2017 | | | 398 | 40.82% | Issued | 01/06/2017 | | | 291 | 29.85% | Issued | 01/05/2017 | | | 379 | 38.87% | Issued | 01/04/2017 | | | 404 | 41.44% | Issued | 01/03/2017 | | | 383 | 39.28% | Redeemed | 01/02/2017 | | | 432 | 44.31% | Redeemed | 01/01/2017 | | | 461 | 47.28% | Redeemed | Dec-16 | 0 | 495 | 495 | 50.77% | Issued | Nov-16 | 0 | 549 | 549 | 56.31% | Issued | Oct-16 | 0 | 590 | 590 | 60.51% | Issued | Sep-16 | 0 | 514 | 514 | 52.72% | Issued | Aug-16 | 0 | 563 | 563 | 57.74% | Issued | Jul-16 | 0 | 528 | 528 | 54.15% | Issued | Jul-16 | 0 | 528 | 528 | 54.15% | Pending Tr | Jun-16 | 0 | 575 | 575 | 58.97% | Issued | Jun-16 | 0 | 575 | 575 | 58.97% | Pending Tr | May-16 | 0 | 539 | 539 | 55.28% | Issued | Apr-16 | 0 | 620 | 620 | 63.59% | Issued | Feb-16 | 0 | 616 | 616 | 63.18% | Redeemed | Jan-16 | 0 | 668 | 668 | 68.51% | Redeemed | Nov-15 | 0 | 666 | 666 | 68.31% | Redeemed | Oct-15 | 0 | 709 | 709 | 72.72% | Redeemed | Sep-15 | 0 | 627 | 627 | 64.31% | Redeemed | Aug-15 | 0 | 486 | 486 | 49.85% | Redeemed | Jul-15 | 352 | 347 | 351 | 36.00% | Redeemed | Jun-15 | 475 | 476 | 476 | 48.82% | Redeemed | May-15 | 493 | 493 | 493 | 50.56% | Redeemed | Apr-15 | 541 | 540 | 540 | 55.38% | Redeemed | Mar-15 | 583 | 583 | 583 | 59.79% | Redeemed | Feb-15 | 560 | 560 | 560 | 57.44% | Redeemed | Jan-15 | 534 | 534 | 534 | 54.77% | Redeemed | Dec-14 | 610 | 610 | 610 | 62.56% | Redeemed | Nov-14 | 468 | 465 | 468 | 48.00% | Redeemed | Oct-14 | 508 | 505 | 508 | 52.10% | Redeemed | Sep-14 | 345 | 341 | 344 | 35.28% | Redeemed | Aug-14 | 351 | 349 | 352 | 36.10% | Redeemed | Jul-14 | 350 | 345 | 350 | 35.90% | Redeemed | Jun-14 | 484 | 484 | 484 | 49.64% | Redeemed | May-14 | 508 | 508 | 508 | 52.10% | Redeemed | Apr-14 | 519 | 519 | 519 | 53.23% | Redeemed | Mar-14 | 547 | 547 | 547 | 56.10% | Redeemed | Feb-14 | 392 | 388 | 391 | 40.10% | Redeemed | Jan-14 | 443 | 444 | 444 | 45.54% | Redeemed | Dec-13 | 391 | 391 | 391 | 40.10% | Redeemed | Nov-13 | 408 | 408 | 408 | 41.85% | Redeemed | Oct-13 | 379 | 379 | 379 | 38.87% | Redeemed | Sep-13 | 352 | 352 | 351 | 36.00% | Redeemed | Aug-13 | 324 | 324 | 324 | 33.23% | Redeemed | Jul-13 | 341 | 341 | 341 | 34.97% | Redeemed | Jun-13 | 336 | 336 | 336 | 34.46% | Redeemed | May-13 | 357 | 357 | 357 | 36.62% | Redeemed | Apr-13 | 357 | 358 | 358 | 36.72% | Redeemed | Mar-13 | 394 | 394 | 394 | 40.41% | Redeemed | Feb-13 | 308 | 306 | 309 | 31.69% | Redeemed | Jan-13 | 436 | 435 | 435 | 44.62% | Redeemed | Dec-12 | 469 | 469 | 469 | 48.10% | Redeemed | Nov-12 | 467 | 467 | 467 | 47.90% | Redeemed | Oct-12 | 406 | 404 | 406 | 41.64% | Redeemed | Sep-12 | 349 | 348 | 349 | 35.79% | Redeemed | Aug-12 | 348 | 347 | 347 | 35.59% | Redeemed | Jul-12 | 335 | 335 | 335 | 34.36% | Redeemed | Jun-12 | 335 | 336 | 336 | 34.46% | Redeemed | May-12 | 351 | 351 | 351 | 36.00% | Redeemed | Apr-12 | 401 | 401 | 401 | 41.13% | Redeemed | Mar-12 | 433 | 433 | 433 | 44.41% | Redeemed | Feb-12 | 428 | 428 | 428 | 43.90% | Redeemed | Jan-12 | 473 | 473 | 473 | 48.51% | Redeemed | Dec-11 | 505 | 505 | 505 | 51.79% | Redeemed | Nov-11 | 433 | 433 | 433 | 44.41% | Redeemed | Oct-11 | 410 | 410 | 410 | 42.05% | Redeemed | Sep-11 | 370 | 370 | 370 | 37.95% | Redeemed | Aug-11 | 393 | 393 | 393 | 40.31% | Redeemed | Jul-11 | 379 | 379 | 379 | 38.87% | Redeemed | Jun-11 | 345 | 345 | 345 | 35.38% | Redeemed | May-11 | 347 | 348 | 348 | 35.69% | Redeemed | Apr-11 | 389 | 388 | 388 | 39.79% | Redeemed | Mar-11 | 369 | 370 | 370 | 37.95% | Redeemed | Feb-11 | 256 | 253 | 255 | 26.15% | Redeemed | Jan-11 | 294 | 295 | 295 | 30.26% | Redeemed | Dec-10 | 269 | 269 | 269 | 27.59% | Redeemed | Nov-10 | 289 | 289 | 289 | 29.64% | Redeemed | Oct-10 | 296 | 295 | 295 | 30.26% | Redeemed |
|
Project Info |
Sorry I found no matches, Please try again.
|
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017
Simon Mallett |
|