Kilbraur Wind Farm (Wind , Active) Location in the UK : Scotland, Sutherland - Strath Brora Type of installation: Wind on/offshore: on Turbines :19 Capacity : 67.5 MW Approx Date of 1st power generation: June 2008
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
Includes Kilbraur Extension Assumes Nordex N90
The wind farm has nineteen 2.5Mw turbines. Each turbine is around 115 m high from its base to the highest point of its blade. When the wind farm is operating fully it will generate enough clean, green electricity to supply around 27,000 homes and help reduce reliance on existing less environmentally-friendly energy resources.
The Kilbraur Extension September 2011 Adds a further 8 turbines generating 20MW
Model: |
Nordex N90
|
Start Speed: |
4
|
Capacity: |
2.3
|
Optimal Speed: |
12
|
Rotor Diameter: |
90
|
Stop Speed: |
25
|
Hub Height |
70 Avg for all turbines:70
|
Avg. Elevation: |
258
|
Web Page: |
http://www.nordex-online.com/en/produkte-service/wind-turbines/n90-25-mw.html |
Comment: |
N90 suits inland locations
|
Kilbraur Wind Farm Farlarly Road Sutherland IV28 3YE Scotland
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Kilbraur Windfarm Farlary - Extension 20 MW
|
Energy Type: |
Wind Onshore |
County: |
Highland Country: Scotland LPA: Scottish Government (S36)
|
Site ID and Reference: |
2673 / A0027
District:
|
Applicant: |
Falck Renewables
Application :
09/00111/S36SU
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
8 |
Turbine Capacity: |
2.5 |
Height of Turbines: |
|
Calculated capacity: |
20 |
Site Address: |
Dunrobin Glen, Golspie, The Highlands. KW10 6SE
|
|
|
County: |
Highland Region: Scotland
|
OS Coordinates: |
283124 / 283124
|
Development Status: |
Operational
|
Application Submitted: |
3/13/2009
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
12/1/2010
|
|
|
Generator Live |
9/1/2011
|
This Record Last Updated: |
10/17/2011
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Kilbraur Windfarm 47.5 MW
|
Energy Type: |
Wind Onshore |
County: |
Highland Country: Scotland LPA: Highland Council
|
Site ID and Reference: |
3202 / N00215W
District:
|
Applicant: |
Renewable Development Company (RDC)
Application :
SU2004125
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
19 |
Turbine Capacity: |
2.5 |
Height of Turbines: |
|
Calculated capacity: |
47.5 |
Site Address: |
Rogart, Sutherland
(former Strath Brora Site)
|
|
|
County: |
Highland Region: Scotland
|
OS Coordinates: |
278550 / 278550
|
Development Status: |
Operational
|
Application Submitted: |
9/4/2003
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
9/1/2007
|
|
|
Generator Live |
6/14/2008
|
This Record Last Updated: |
10/23/2009
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Kilbraur Wind Farm
|
Generator Type: |
Wind
|
Scheme : |
REGO
|
Generator ID: |
G01476NWSC
|
Capacity: |
67500
|
Status: |
Live
|
Accreditation Date: |
9/4/2003
|
|
|
Commission Date: |
6/14/2008
|
|
|
Applicant: |
Falck Renewables Ltd
|
Applicant Address: |
7-10 Beaumont Mews
London
W1G 6EB
|
Address: |
Kilbraur Wind Farm
Farlarly Road
Sutherland
IV28 3YE
Scotland
|
|
Assumptions: Capacity: 67500kW 67.5 MW, Thus over the month Capacity * 720 hours per month = 48600 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/04/2018 | | | 14413 | 21.35% | Issued | 01/03/2018 | | | 20351 | 30.15% | Issued | 01/02/2018 | | | 15566 | 23.06% | Issued | 01/01/2018 | | | 18078 | 26.78% | Issued | 01/12/2017 | | | 16858 | 24.97% | Issued | 01/11/2017 | | | 20326 | 30.11% | Issued | 01/10/2017 | | | 18350 | 27.19% | Issued | 01/09/2017 | | | 12605 | 18.67% | Issued | 01/08/2017 | | | 9707 | 14.38% | Issued | 01/07/2017 | | | 9990 | 14.80% | Issued | 01/06/2017 | | | 8304 | 12.30% | Issued | 01/05/2017 | | | 11196 | 16.59% | Issued | 01/04/2017 | | | 16076 | 23.82% | Issued | 01/03/2017 | | | 17202 | 25.48% | Redeemed | 01/02/2017 | | | 17540 | 25.99% | Redeemed | 01/01/2017 | | | 18409 | 27.27% | Redeemed | Dec-16 | 0 | 19737 | 19736 | 29.24% | Issued | Nov-16 | 0 | 12649 | 12649 | 18.74% | Issued | Oct-16 | 0 | 14530 | 14531 | 21.53% | Issued | Sep-16 | 0 | 11216 | 11216 | 16.62% | Issued | Aug-16 | 0 | 10261 | 10313 | 15.28% | Issued | Jul-16 | 0 | 8890 | 8890 | 13.17% | Issued | Jul-16 | 0 | 8890 | 8890 | 13.17% | Issued | Jun-16 | 0 | 8856 | 8855 | 13.12% | Issued | Jun-16 | 0 | 8856 | 8855 | 13.12% | Issued | May-16 | 0 | 8985 | 8985 | 13.31% | Issued | Apr-16 | 0 | 15441 | 15441 | 22.88% | Issued | Mar-16 | 0 | 10766 | 10766 | 15.95% | Redeemed | Feb-16 | 0 | 14527 | 14528 | 21.52% | Redeemed | Jan-16 | 0 | 16153 | 16153 | 23.93% | Redeemed | Dec-15 | 0 | 22377 | 22377 | 33.15% | Redeemed | Nov-15 | 0 | 20305 | 20305 | 30.08% | Redeemed | Oct-15 | 0 | 13415 | 13415 | 19.87% | Redeemed | Sep-15 | 0 | 12149 | 12149 | 18.00% | Redeemed | Aug-15 | 0 | 10700 | 10700 | 15.85% | Redeemed | Jul-15 | 10471 | 10472 | 10472 | 15.51% | Redeemed | Jun-15 | 12200 | 12200 | 12200 | 18.07% | Redeemed | May-15 | 20440 | 20439 | 20439 | 30.28% | Redeemed | Apr-15 | 13751 | 13751 | 13751 | 20.37% | Redeemed | Mar-15 | 18946 | 18946 | 18946 | 28.07% | Redeemed | Feb-15 | 18792 | 18792 | 18792 | 27.84% | Redeemed | Jan-15 | 27079 | 27080 | 27080 | 40.12% | Redeemed | Dec-14 | 23410 | 23409 | 23409 | 34.68% | Redeemed | Nov-14 | 14022 | 14022 | 14022 | 20.77% | Redeemed | Oct-14 | 14152 | 14152 | 14152 | 20.97% | Redeemed | Sep-14 | 8925 | 8879 | 8925 | 13.22% | Redeemed | Aug-14 | 12629 | 12629 | 12629 | 18.71% | Redeemed | Jul-14 | 10596 | 10596 | 10596 | 15.70% | Redeemed | Jun-14 | 6767 | 6733 | 6767 | 10.03% | Redeemed | May-14 | 8615 | 8616 | 8616 | 12.76% | Redeemed | Apr-14 | 15793 | 15792 | 15793 | 23.40% | Redeemed | Mar-14 | 16127 | 16126 | 16127 | 23.89% | Redeemed | Feb-14 | 22352 | 22353 | 22353 | 33.12% | Redeemed | Jan-14 | 21148 | 21148 | 21148 | 31.33% | Redeemed | Dec-13 | 27222 | 27222 | 27222 | 40.33% | Redeemed | Nov-13 | 18717 | 18718 | 18660 | 27.64% | Redeemed | Oct-13 | 13991 | 13990 | 1 | 0.00% | Redeemed | Sep-13 | 8106 | 8057 | 8105 | 12.01% | Redeemed | Aug-13 | 8025 | 7965 | 8025 | 11.89% | Redeemed | Jul-13 | 10488 | 10489 | 10488 | 15.54% | Redeemed | Jun-13 | 9527 | 9469 | 9527 | 14.11% | Redeemed | May-13 | 14639 | 14638 | 14639 | 21.69% | Redeemed | Apr-13 | 18026 | 18026 | 18026 | 26.71% | Redeemed | Mar-13 | 17776 | 17776 | 17776 | 26.33% | Redeemed | Feb-13 | 14710 | 14711 | 14710 | 21.79% | Redeemed | Jan-13 | 20950 | 20950 | 20950 | 31.04% | Redeemed | Dec-12 | 18399 | 18400 | 18399 | 27.26% | Redeemed | Nov-12 | 14703 | 14702 | 14702 | 21.78% | Redeemed | Oct-12 | 9607 | 9608 | 9607 | 14.23% | Redeemed | Sep-12 | 21195 | 21195 | 21195 | 31.40% | Redeemed | Aug-12 | 10581 | 10581 | 10581 | 15.68% | Redeemed | Jul-12 | 10458 | 10458 | 10458 | 15.49% | Redeemed | Jun-12 | 8678 | 8678 | 8678 | 12.86% | Redeemed | May-12 | 9589 | 9589 | 9589 | 14.21% | Redeemed | Apr-12 | 8899 | 8832 | 8899 | 13.18% | Redeemed | Mar-12 | 18867 | 18867 | 18868 | 27.95% | Redeemed | Feb-12 | 19786 | 19785 | 19785 | 29.31% | Redeemed | Jan-12 | 20579 | 20580 | 20579 | 30.49% | Redeemed | Dec-11 | 21973 | 21972 | 21973 | 32.55% | Redeemed | Nov-11 | 18170 | 18170 | 18170 | 26.92% | Redeemed | Oct-11 | 18500 | 18500 | 18500 | 27.41% | Redeemed | Sep-11 | 14920 | 14920 | 14920 | 22.10% | Redeemed | Aug-11 | 11778 | 11778 | 11778 | 17.45% | Redeemed | Jul-11 | 8358 | 8315 | 8358 | 12.38% | Redeemed | Jun-11 | 7582 | 7583 | 7583 | 11.23% | Redeemed | May-11 | 14460 | 14459 | 14459 | 21.42% | Redeemed | Apr-11 | 9281 | 9281 | 9281 | 13.75% | Redeemed | Mar-11 | 11869 | 11869 | 11869 | 17.58% | Redeemed | Feb-11 | 13927 | 13928 | 13928 | 20.63% | Redeemed | Jan-11 | 10711 | 10711 | 10711 | 15.87% | Redeemed | Dec-10 | 8499 | 8456 | 8499 | 12.59% | Redeemed | Nov-10 | 9592 | 9592 | 9592 | 14.21% | Redeemed |
|
Capacity: 95 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 25 m/s (55.925 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 11/21/2024 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Monday, September 9, 2024 00:00
How many more wind turbines will the UK build?. The government says it wants to generate enough wind energy to be able to power every home in the UK by 2030. Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Surging seas are coming for us all, warns UN chief The World Meteorological Organization’s State of the Climate in the South West Pacific, external report says this region faces a triple whammy of an accelerating rise in the sea level, a warming of the ocean and acidification Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Nine offshore wind farm projects awarded in UK auction The new offshore projects include what will be Europe's largest and second-largest wind farms, Hornsea 3 and Hornsea 4, which will be built off the Yorkshire coast by Ørsted Source: bbc, Date and Time of entry: Wednesday, September 4, 2024 00:00
Carn Nicholas Drone footage Date and Time of entry: Tuesday, March 19, 2024 00:00
|
|
©2017
Simon Mallett |
|