Loading
Page views this IP this session = 1 of 10 unsubscribed pagesNorth Rhins Wind Farm
Click here for Generation Forecast for wind farms based on Met office data
North Rhins Wind Farm (Wind , Active) Location in the UK : Scotland, Dumfries & Galloway Type of installation: Wind on/offshore: on Turbines :11 Capacity : 22 MW Approx Date of 1st power generation: Jan 2010
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
The wind farm consists of 11 turbines with a total installed capacity of 22MW. The turbines generate enough electricty to power the equivalent of 14,000 average households.
Dumfries and Galloway Council’s Wigtown Area Committee approved our planning application on 14 March 2008. A planning agreement is currently being negotiated between the project company and the council. We expect the wind farm to be generating renewable electricity during 2009.
Model: |
Vestas V80
|
Start Speed: |
4
|
Capacity: |
2
|
Optimal Speed: |
15
|
Rotor Diameter: |
80
|
Stop Speed: |
25
|
Hub Height |
60 Avg for all turbines:50
|
Avg. Elevation: |
148
|
Web Page: |
|
Comment: |
|
Enoch FarmPortpatrick DG9 8JG Scotland
Relationship |
Company (For:
North Rhins
) |
Sorry I found no matches, Please try again.
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
North Rhins 22 MW
|
Energy Type: |
Wind Onshore |
County: |
Dumfries and Galloway Country: Scotland LPA: Dumfries and Galloway Council
|
Site ID and Reference: |
4508 / EN00234
District:
|
Applicant: |
Greencoat UK Wind
Application :
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
11 |
Turbine Capacity: |
2 |
Height of Turbines: |
|
Calculated capacity: |
22 |
Site Address: |
North Rhins
Stranraer
Dumfries and Galloway
|
|
|
County: |
Dumfries and Galloway Region: Scotland
|
OS Coordinates: |
201980 / 201980
|
Development Status: |
Operational
|
Application Submitted: |
1/15/2007
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
10/1/2009
|
|
|
Generator Live |
1/20/2010
|
This Record Last Updated: |
1/5/2015
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Wind Energy (North Rhins) Limited
|
Generator Type: |
On-shore wind (ROS code = SQ)
|
Scheme : |
RO
|
Generator ID: |
R00099SQSC
|
Capacity: |
22000
|
Status: |
Live
|
Accreditation Date: |
1/15/2007
|
|
|
Commission Date: |
11/1/2009
|
|
|
Applicant: |
North Rhins Wind Farm Limited
|
Applicant Address: |
27-28 Eastcastle Street
London
W1W 8DH
England
|
Address: |
Wind Energy (North Rhins) LTD
Enoch Farm
Portpatrick
DG9 8JG
Scotland
|
Site Name: |
Wind Energy (North Rhins) Limited
|
Generator Type: |
Wind
|
Scheme : |
REGO
|
Generator ID: |
G01555NWSC
|
Capacity: |
22000
|
Status: |
Live
|
Accreditation Date: |
1/15/2007
|
|
|
Commission Date: |
11/1/2009
|
|
|
Applicant: |
North Rhins Wind Farm Limited
|
Applicant Address: |
27-28 Eastcastle Street
London
W1W 8DH
England
|
Address: |
Wind Energy (North Rhins) LTD
Enoch Farm
Portpatrick
DG9 8JG
Scotland
|
|
Assumptions: Capacity: 22000kW 22 MW, Thus over the month Capacity * 720 hours per month = 15840 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/04/2018 | | | 5020 | 22.82% | Issued | 01/03/2018 | | | 6569 | 29.86% | Issued | 01/02/2018 | | | 7006 | 31.85% | Issued | 01/01/2018 | | | 10029 | 45.59% | Issued | 01/12/2017 | | | 7232 | 32.87% | Issued | 01/11/2017 | | | 7513 | 34.15% | Issued | 01/10/2017 | | | 8333 | 37.88% | Issued | 01/09/2017 | | | 6124 | 27.84% | Issued | 01/08/2017 | | | 4495 | 20.43% | Issued | 01/07/2017 | | | 3889 | 17.68% | Issued | 01/06/2017 | | | 5848 | 26.58% | Issued | 01/05/2017 | | | 4189 | 19.04% | Issued | 01/04/2017 | | | 5850 | 26.59% | Issued | 01/03/2017 | | | 5824 | 26.47% | Issued | 01/02/2017 | | | 7551 | 34.32% | Issued | 01/01/2017 | | | 7880 | 35.82% | Issued | Dec-16 | 0 | 7937 | 7937 | 36.08% | Issued | Nov-16 | 0 | 5992 | 5992 | 27.24% | Issued | Oct-16 | 0 | 5336 | 5336 | 24.25% | Issued | Sep-16 | 0 | 5736 | 5736 | 26.07% | Issued | Aug-16 | 0 | 5166 | 5166 | 23.48% | Issued | Jul-16 | 0 | 3610 | 3610 | 16.41% | Issued | Jul-16 | 0 | 3610 | 3610 | 16.41% | Issued | May-16 | 0 | 4660 | 4660 | 21.18% | Issued | Mar-16 | 0 | 4748 | 4748 | 21.58% | Issued | Feb-16 | 0 | 7176 | 7176 | 32.62% | Issued | Dec-15 | 0 | 10790 | 10790 | 49.05% | Issued | Nov-15 | 0 | 8987 | 8987 | 40.85% | Issued | Oct-15 | 0 | 5094 | 5094 | 23.15% | Issued | Sep-15 | 0 | 4564 | 4564 | 20.75% | Issued | Aug-15 | 0 | 4811 | 4811 | 21.87% | Issued | Jul-15 | 4279 | 4279 | 4279 | 19.45% | Expired | Jun-15 | 4111 | 4111 | 4111 | 18.69% | Expired | May-15 | 6747 | 6748 | 6748 | 30.67% | Expired | Apr-15 | 4002 | 4002 | 4002 | 18.19% | Expired | Mar-15 | 8170 | 8170 | 8170 | 37.14% | Expired | Feb-15 | 6859 | 6859 | 6859 | 31.18% | Expired | Jan-15 | 10900 | 10900 | 10900 | 49.55% | Expired | Dec-14 | 9019 | 9019 | 8535 | 38.80% | Redeemed | Nov-14 | 6222 | 6222 | 6222 | 28.28% | Redeemed | Oct-14 | 7315 | 7315 | 7315 | 33.25% | Redeemed | Sep-14 | 1914 | 1902 | 1914 | 8.70% | Redeemed | Aug-14 | 5556 | 5557 | 5557 | 25.26% | Redeemed | Jul-14 | 2788 | 2788 | 2788 | 12.67% | Redeemed | Jun-14 | 2837 | 2838 | 2838 | 12.90% | Redeemed | May-14 | 3137 | 3136 | 3136 | 14.25% | Redeemed | Apr-14 | 5301 | 5301 | 5301 | 24.10% | Redeemed | Mar-14 | 7577 | 7577 | 7577 | 34.44% | Redeemed | Feb-14 | 9476 | 9476 | 9476 | 43.07% | Redeemed | Jan-14 | 8134 | 8134 | 8134 | 36.97% | Redeemed | Dec-13 | 10982 | 10982 | 10982 | 49.92% | Redeemed | Nov-13 | 6227 | 6227 | 6226 | 28.30% | Redeemed | Oct-13 | 8463 | 8463 | 8463 | 38.47% | Redeemed | Sep-13 | 5919 | 5919 | 5919 | 26.90% | Redeemed | Aug-13 | 4245 | 4245 | 4245 | 19.30% | Redeemed | Jul-13 | 2205 | 2182 | 2205 | 10.02% | Redeemed | Jun-13 | 3482 | 3464 | 3482 | 15.83% | Redeemed | May-13 | 6861 | 6861 | 6861 | 31.19% | Redeemed | Apr-13 | 6968 | 6969 | 6969 | 31.68% | Redeemed | Mar-13 | 6051 | 6050 | 6050 | 27.50% | Redeemed | Feb-13 | 5671 | 5671 | 5671 | 25.78% | Redeemed | Jan-13 | 8342 | 8342 | 8342 | 37.92% | Redeemed | Dec-12 | 8368 | 8369 | 8369 | 38.04% | Redeemed | Nov-12 | 6629 | 6629 | 6629 | 30.13% | Redeemed | Oct-12 | 4578 | 4578 | 4578 | 20.81% | Redeemed | Sep-12 | 7029 | 7029 | 7029 | 31.95% | Redeemed | Aug-12 | 5006 | 5006 | 5006 | 22.75% | Redeemed | Jul-12 | 3347 | 3347 | 3347 | 15.21% | Redeemed | Jun-12 | 4082 | 4082 | 4082 | 18.55% | Redeemed | May-12 | 3127 | 3108 | 3127 | 14.21% | Redeemed | Apr-12 | 5076 | 5076 | 5076 | 23.07% | Redeemed | Mar-12 | 5250 | 5251 | 5251 | 23.87% | Redeemed | Feb-12 | 6834 | 6834 | 6834 | 31.06% | Redeemed | Jan-12 | 9217 | 9217 | 9217 | 41.90% | Redeemed | Dec-11 | 10627 | 10626 | 10626 | 48.30% | Redeemed | Nov-11 | 8985 | 8985 | 8985 | 40.84% | Redeemed | Oct-11 | 8730 | 8731 | 8731 | 39.69% | Redeemed | Sep-11 | 7652 | 7652 | 7652 | 34.78% | Redeemed | Aug-11 | 3799 | 3799 | 3799 | 17.27% | Redeemed | Jul-11 | 3872 | 3872 | 3872 | 17.60% | Redeemed | Jun-11 | 3600 | 3600 | 3600 | 16.36% | Redeemed | May-11 | 9006 | 9007 | 9007 | 40.94% | Redeemed | Apr-11 | 4813 | 4813 | 4813 | 21.88% | Redeemed | Mar-11 | 3560 | 3542 | 3560 | 16.18% | Redeemed | Feb-11 | 7125 | 7125 | 7125 | 32.39% | Redeemed | Jan-11 | 5862 | 5861 | 5861 | 26.64% | Redeemed | Dec-10 | 4559 | 4559 | 4559 | 20.72% | Redeemed | Nov-10 | 5614 | 5615 | 5615 | 25.52% | Redeemed | Oct-10 | 6901 | 6901 | 6901 | 31.37% | Redeemed |
|
Capacity: 48 Start Speed: 5 m/s (11.185 mph) Optimum Speed: 15 m/s (33.555 mph) Stop Speed: 25 m/s (55.925 mph)
Local Weather Station: Elevation of Weather Station:
Date for Wind forecast: 4/3/2025 Wind Speed at Weather Station: mph Wind Direction: Outputratio = 0.00 Output of Wind Farm = 0.0
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017
Simon Mallett |
|