Loading
Page views this IP this session = 3 of 10 unsubscribed pagesLairg
Lairg (Hydro , Active) Location in the UK : Scotland, Type of installation: Hydro on/offshore: on Turbines :0 Capacity : 3.5 MW Approx Date of 1st power generation: January 1959
/YES
Lairg Wind Farm is now fully operational after construction work finished at the beginning of 2012. Lairg, located in the Scottish Highlands, consists of three Nordex N80 turbines and will generate an output of 7.5MW. We are now undergoing a period of post construction restoration around the site. Lairg represents ABO Wind’s first build in the UK with more projects at either planning or acquisition stages. Lairg
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Lairg Wind Farm 7.5 MW
|
Energy Type: |
Wind Onshore |
County: |
Highland Country: Scotland LPA: Highland Council
|
Site ID and Reference: |
2796 / AA734
District:
|
Applicant: |
ABO Wind
Application :
06/00376/FULSU
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
3 |
Turbine Capacity: |
2.5 |
Height of Turbines: |
|
Calculated capacity: |
7.5 |
Site Address: |
Land To South Of Toroboll Lairg Highland
|
|
|
County: |
Highland Region: Scotland
|
OS Coordinates: |
261293 / 261293
|
Development Status: |
Operational
|
Application Submitted: |
9/5/2006
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
|
Construction Date: |
|
|
|
Generator Live |
1/1/2012
|
This Record Last Updated: |
4/19/2012
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
|
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
|
Site Name: |
Lairg Wind Farm Limited
|
Generator Type: |
On-shore wind (ROS code = SQ)
|
Scheme : |
RO
|
Generator ID: |
R00182SQSC
|
Capacity: |
7500
|
Status: |
Live
|
Accreditation Date: |
9/5/2006
|
|
|
Commission Date: |
2/9/2012
|
|
|
Applicant: |
Lairg Wind Farm Limited
|
Applicant Address: |
1 Houstoun Interchange
Livingston
EH54 5DW
Scotland
|
Address: |
Lairg Wind Farm
Torroble Road
Lairg
IV274DQ
Scotland
|
Site Name: |
Lairg Wind Farm Limited
|
Generator Type: |
Wind
|
Scheme : |
REGO
|
Generator ID: |
G01786NWSC
|
Capacity: |
7500
|
Status: |
Live
|
Accreditation Date: |
9/5/2006
|
|
|
Commission Date: |
2/9/2012
|
|
|
Applicant: |
Lairg Wind Farm Limited
|
Applicant Address: |
1 Houstoun Interchange
Livingston
EH54 5DW
Scotland
|
Address: |
Lairg Wind Farm
Torroble Road
Lairg
IV274DQ
Scotland
|
|
Assumptions: Capacity: 7500kW 7.5 MW, Thus over the month Capacity * 720 hours per month = 5400 MWh
|
Output Period |
LECs Issued |
ROCs Issued |
REGO Certs |
Capacity Factor |
Status |
01/04/2018 | | | 1376 | 18.35% | Issued | 01/03/2018 | | | 2055 | 27.40% | Issued | 01/02/2018 | | | 1364 | 18.19% | Issued | 01/01/2018 | | | 1892 | 25.23% | Issued | 01/12/2017 | | | 1584 | 21.12% | Issued | 01/11/2017 | | | 1832 | 24.43% | Issued | 01/10/2017 | | | 2137 | 28.49% | Issued | 01/09/2017 | | | 1331 | 17.75% | Issued | 01/08/2017 | | | 1053 | 14.04% | Issued | 01/07/2017 | | | 1155 | 15.40% | Issued | 01/06/2017 | | | 1170 | 15.60% | Issued | 01/05/2017 | | | 1191 | 15.88% | Issued | 01/04/2017 | | | 2112 | 28.16% | Issued | 01/03/2017 | | | 1395 | 18.60% | Issued | 01/02/2017 | | | 380 | 5.07% | Redeemed | 01/02/2017 | | | 1395 | 18.60% | Redeemed | 01/01/2017 | | | 1693 | 22.57% | Redeemed | Dec-16 | 0 | 1962 | 2029 | 27.05% | Issued | Nov-16 | 0 | 1140 | 1186 | 15.81% | Issued | Oct-16 | 0 | 1417 | 1465 | 19.53% | Issued | Sep-16 | 0 | 1333 | 1378 | 18.37% | Issued | Aug-16 | 0 | 964 | 973 | 12.97% | Issued | Jul-16 | 0 | 925 | 933 | 12.44% | Issued | Jun-16 | 0 | 896 | 6 | 0.08% | Issued | May-16 | 0 | 959 | 7 | 0.09% | Issued | Apr-16 | 0 | 1367 | 1367 | 18.23% | Issued | Feb-16 | 0 | 1217 | 1217 | 16.23% | Redeemed | Jan-16 | 0 | 1417 | 1417 | 18.89% | Redeemed | Dec-15 | 0 | 2086 | 2086 | 27.81% | Redeemed | Nov-15 | 0 | 1712 | 1712 | 22.83% | Redeemed | Oct-15 | 0 | 1194 | 7 | 0.09% | Issued | Sep-15 | 0 | 982 | 982 | 13.09% | Redeemed | Aug-15 | 0 | 1008 | 7 | 0.09% | Issued | Jul-15 | 962 | 962 | 962 | 12.83% | Redeemed | Jun-15 | 1108 | 1107 | 1108 | 14.77% | Redeemed | May-15 | 1918 | 1922 | 1918 | 25.57% | Redeemed | Apr-15 | 841 | 841 | 841 | 11.21% | Redeemed | Mar-15 | 1744 | 1749 | 1744 | 23.25% | Redeemed | Feb-15 | 1710 | 1714 | 1710 | 22.80% | Redeemed | Jan-15 | 1918 | 1922 | 1918 | 25.57% | Redeemed | Dec-14 | 1822 | 1826 | 1822 | 24.29% | Redeemed | Nov-14 | 1410 | 1416 | 1410 | 18.80% | Redeemed | Oct-14 | 1645 | 1651 | 1645 | 21.93% | Redeemed | Sep-14 | 682 | 682 | 682 | 9.09% | Redeemed | Aug-14 | 1353 | 1359 | 1353 | 18.04% | Redeemed | Jul-14 | 900 | 900 | 900 | 12.00% | Redeemed | Jun-14 | 637 | 637 | 637 | 8.49% | Redeemed | May-14 | 726 | 726 | 726 | 9.68% | Redeemed | Apr-14 | 1423 | 1423 | 7 | 0.09% | Expired | Mar-14 | 479 | 479 | 479 | 6.39% | Redeemed | Feb-14 | 1947 | 1952 | 1947 | 25.96% | Redeemed | Jan-14 | 2108 | 2113 | 2108 | 28.11% | Redeemed | Dec-13 | 2239 | 2245 | 2239 | 29.85% | Redeemed | Nov-13 | 1479 | 1485 | 1479 | 19.72% | Redeemed | Oct-13 | 1593 | 1599 | 1593 | 21.24% | Redeemed | Sep-13 | 1315 | 1316 | 1315 | 17.53% | Redeemed | Aug-13 | 1111 | 1111 | 8 | 0.11% | Expired | Jul-13 | 891 | 891 | 891 | 11.88% | Redeemed | Jun-13 | 805 | 805 | 805 | 10.73% | Redeemed | May-13 | 1286 | 1285 | 1286 | 17.15% | Redeemed | Apr-13 | 1584 | 1588 | 1584 | 21.12% | Redeemed | Mar-13 | 1606 | 1611 | 1606 | 21.41% | Redeemed | Feb-13 | 1114 | 1114 | 1114 | 14.85% | Redeemed | Jan-13 | 1716 | 1716 | 1716 | 22.88% | Redeemed | Dec-12 | 1482 | 1483 | 1482 | 19.76% | Redeemed | Nov-12 | 1163 | 1163 | 1163 | 15.51% | Redeemed | Oct-12 | 778 | 778 | 778 | 10.37% | Redeemed | Sep-12 | 1605 | 1613 | 1605 | 21.40% | Redeemed | Aug-12 | 862 | 862 | 862 | 11.49% | Redeemed | Jul-12 | 701 | 700 | 701 | 9.35% | Redeemed | Jun-12 | 881 | 881 | 881 | 11.75% | Redeemed | May-12 | 906 | 907 | 13 | 0.17% | Expired |
|
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017
Simon Mallett |
|