Inverclyde Wind Farm (Wind , Agreed/Planning) Location in the UK : Scotland, greenock Type of installation: Wind on/offshore: on Turbines :8 Capacity : 24 MW Approx Date of 1st power generation:
Wind Turbines, Wind Farm, Renewable Energy, Green Power
/YES
The proposal includes 10 wind turbines with associated infrastructure including:
• 10, three bladed, horizontal axis wind turbines, each up to a maximum blade tip height of 110 m (above ground level), rated at between 2 MW and 3 MW each, and with a maximum hub height of 65 m, all located to the west of the B788;
• external turbine transformers and turbine switchgear next to each turbine;
• a stone hardstanding area at each turbine location for use by the cranes erecting each turbine; Known as Corlic Hill
Model: |
Enercon E82
|
Start Speed: |
4
|
Capacity: |
2
|
Optimal Speed: |
13.5
|
Rotor Diameter: |
82
|
Stop Speed: |
31
|
Hub Height |
69 Avg for all turbines:
|
Avg. Elevation: |
|
Web Page: |
http://www.enercon.de/en-en/62.htm |
Comment: |
Gearless, variable speed, single blade adjustment. Start and Stop: Guesstimate
|
Corlic Hill, near Greenock & Port Glasgow
Please note that where multiple DECC rcords are available, all are shown in order. eg Project then repowering / extension, or refused project then resubmitted.
Site Name: |
Inverclyde Wind Farm (Corlic Hill) 24 MW
|
Energy Type: |
Wind Onshore |
County: |
Strathclyde Country: Scotland LPA: Inverclyde Council
|
Site ID and Reference: |
4200 / B0645
District:
|
Applicant: |
BayWa r.e. (formerly Forsa)
Application :
13/0199/IC
|
(Go to search to find Application) |
For Wind Farms |
|
Number of Turbines: |
8 |
Turbine Capacity: |
3 |
Height of Turbines: |
|
Calculated capacity: |
24 |
Site Address: |
Corlic Hill, near Greenock & Port Glasgow
|
|
|
County: |
Strathclyde Region: Scotland
|
OS Coordinates: |
229563 / 229563
|
Development Status: |
Operational
|
Application Submitted: |
7/8/2013
|
Planning Permission Granted |
|
Application Determined: |
|
Permission refused: |
12/4/2014
|
Construction Date: |
5/15/2019
|
|
|
Generator Live |
2/20/2021
|
This Record Last Updated: |
4/12/2021
|
RO Banding (ROC/MWh) |
|
FiT Tariff (p/kWh): |
|
|
--- Additional Dates where relevant ---- |
Application Withdrawn: |
|
|
|
Permission Expiration Date: |
|
|
|
Secretary of State - |
Appeal Lodged: |
3/3/2015 |
Called In: |
|
Appeal Withdrawn: |
|
Refusal: |
|
Appeal Refused: |
|
Granted: |
|
Appeal Granted: |
12/4/2014 |
Project Info |
|
©2018
Simon Mallett |
Latest News Added |
Larport Solar Farm The land identified for the solar project is to the south of the Clay Hill Pit Substation at Dormington and has been chosen for its potential to deliver solar powered electricity. Date and Time of entry: Thursday, January 2, 2025 00:00
Larport Solar Farm Larport Solar Farm is a 45MW project in Herefordshire, UK. It was the first solar PV project developed by Conrad Energy. Ethical Power was selected as the principal contractor Date and Time of entry: Thursday, January 2, 2025 00:00
Bracks Solar Farm Bracks Farm Solar Park Limited is building a 30MWp solar farm in Cambridgeshire. It has the capacity to produce enough electricity to power approximately 8,000 households per year*. Date and Time of entry: Thursday, January 2, 2025 00:00
Northfield House Farm Solar PV Park, UK Northfield House Farm Solar PV Park is a 26MW solar PV power project. Date and Time of entry: Thursday, January 2, 2025 00:00
Streetfields and Northfield House solar 54,400MWh
renewable energy generated per year Date and Time of entry: Thursday, January 2, 2025 00:00
|
|
©2017
Simon Mallett |
|